Art. 47 BauG · Application for Preliminary Decision

1. To clarify significant construction and usage issues, a preliminary decision may be requested from the competent building permit authority. All documents necessary for the assessment of the request must be enclosed with the application.

2. The same procedure as for a building application is applicable.

3. The preliminary decision is binding for third parties and the building permit authorities concerning the matters addressed, provided that it is still in force and circumstances have not changed. Its effect only takes place within the framework of the subsequent building permit process.

4. A preliminary decision has the same validity period as a building permit.

← Art. 46 BauG Building Act (LC) - Purpose and Scope Art. 48 BauG - Notification Procedure →

Need to analyze how this provision applies to your matter?

Cross-reference this statute against case law, commentaries, and related legislative provisions inside Legislator AI.

Open in Legislator →