Art. 15 Building Act (LC) - Exceptions
Art. 15 BauG · Exceptions
1. Exceptions to the usage regulations of the building zone as well as to other building regulations can be granted by the competent authority if extraordinary circumstances or important reasons exist and neither public interests nor prevailing private interests of a neighbor are impaired.
2. Exceptions for easily removable small or movable structures can be granted on a provisional basis if the applicant can demonstrate a sufficient interest and if no public or prevailing private interests of a neighbor are impaired.
3. For construction projects of a traditional or experimental character, whether from an architectural or structural engineering point of view, the competent authorities may grant exceptions to the provisions set forth in this law, its executive orders, and the BZR, taking into account the rights of third parties as well as landscape and local appearance protection.
4. Exceptions may be granted for a specific duration or with the reservation of revocation at any time. Upon expiration of the period or upon revocation of the exception, the approved structure or facility must be removed by the respective owner within a reasonable period; they have no claim to compensation.
5. Exception permits can be subject to conditions and obligations. In particular, the following conditions are permissible
a) In the event of expropriation, no compensation will be provided for value-increasing expenditures related to works carried out based on an exception permit;
b) Structures and facilities approved for a specific purpose may not be repurposed, subdivided, or converted into condominium ownership;
c) A security for the fulfillment of obligations related to the building permit must be provided.
6. The time limitation, the waiver of compensation (removal and value-added reversal), the prohibition of repurposing, subdivision, and conversion, as well as the obligation to provide security, must be noted in the land register prior to the commencement of construction.
7. Exceptions outside the building zone are governed by federal law. The land use planning protection of structures and facilities outside the building zone can be determined on a case-by-case basis by the KBK.