Art. 10 BauG · Communication, Calculation of Time Limits, Timestamp, and Absence of Qualified Electronic Signatures on the Platform

**1. All digital communications by an authority are conducted by depositing a message to the party on the platform. The retrieval of this message by the party is considered the delivery time of the message and the links contained therein. If the message is not retrieved, it is considered delivered and retrieved, along with the links contained within, no later than 7 days after being deposited on the platform.**

**2. Every digital communication by an authority and each retrieval of a message receives a timestamp, which allows for determining the exact time of deposition of a message to the party and the time of retrieval of a message on the platform.**

**3. Every digital communication by a party receives a timestamp, which allows for determining the exact time of the communication.**

**4. The timestamp can particularly be used to verify whether the deadlines set for the party have been met.**

**5. If the required qualified electronic signature is missing, the authority shall set a deadline for the party to rectify this deficiency. If the missing signature is provided within the set deadline, the deficiency is considered rectified. Otherwise, the document for which the qualified electronic signature is required, as well as any possible enclosures, are deemed inadmissible.**

← Art. 9 BauG Building Act (LC) - Purpose and Scope Art. 11 BauG →

Need to analyze how this provision applies to your matter?

Cross-reference this statute against case law, commentaries, and related legislative provisions inside Legislator AI.

Open in Legislator →

Court Decisions Applying This Provision (2)

A1 07 165 · vs (Art. 10 Abs. 1, 21, 22 Abs. 1 und 4 BauG)
Construction Permit Setback for Underground Access Ramp Upheld
These articles establish the general rules for building distances and the exception for underground structures, which formed the core reasoning for upholding the lower court's decision regarding the ramp.
RVJ 2013 p 7 12 · vs (Art. 10 al. 2 LC)
Municipality v. Property Owner: Building Setbacks for Subterranean Structures
Cited in the reasoning regarding the definition of the distance to the limit.