Act on Quarries (LCar) (LCAR)
Table of Provisions (36)
Statutory Text (36 Articles)
1. All natural deposits, whether exposed or submerged, of substances used in the economy, existing within the earth or on its surface, and not classified under mining laws [A] or hydrocarbon laws [B] (such as deposits of stone, gravel, sand, marl, clay, or peat) are deemed quarries.
2. Substances located below the highest level that the groundwater table can reach are considered submerged substances.
1. Quarries belong to the owner of the land.
1. Operations involving very small quantities of materials are governed by the provisions relating to constructions; the law on spatial planning and constructions (LATC) [C] and the applicable provisions on digs or excavations [D] apply to them.
2. Quarries operated for commercial or industrial purposes, constructions or installations ancillary thereto, as well as land developments or civil engineering works related to the transportation of materials intended for the economy are governed by this law, notably by the law on spatial planning and constructions, as well as by the road law [E].
3. The exploitation of submerged materials is prohibited except in designated zones intended for this purpose.
1. The master plan of quarries delineates the areas suitable for the commercial and industrial exploitation of materials.
2. Its objective is to ensure a continuous supply for the canton.
3. It can be established by the department, a municipality, or a group of municipalities.
4. Its legal scope is governed by Article 31 LATC [C].
1. The master plan for quarries takes into account other master plans that coordinate activities impacting land use planning.
2. It includes an inventory of territories already exploited or under exploitation, the areas that can be used or developed, as well as existing road infrastructures.
3. It specifies the elements to be coordinated with other plans.
4. The procedure of LATC [C] governing master plans is applicable.
1. The commercial or industrial exploitation of new quarries may only take place in an area designated for this purpose and in accordance with the specific operating conditions set for the extraction of materials. These elements are subject to a special plan called the "extraction plan" if there is no extraction zone in the general municipal land use plan.
2. The provisions of Article 24 of the Federal Law on Spatial Planning [F] are reserved, applicable to a minor extension of an operation that benefits from an already granted authorization or to the initiation of a small-scale operation.
3. The extraction plan covers all or part of a deposit and may extend over the territory of one or several municipalities.
4. It may be established at the initiative of the department, the municipality, a group of municipalities, the owners, or future operators if they together hold more than one-fifth of the area included in the plan.
1. The extraction plan shall duly consider the interests of the canton and the region, particularly the preservation of groundwater, agricultural lands, forests, landscapes, the natural environment, the necessity to supply the region with materials, or other public interests.
1. The implementing regulation [G] of the law sets the content of the extraction plans, which shall include the following elements
a. the delimitation of the perimeter of the extraction zone and the areas suitable for extraction;
b. land use (housing, roads, etc.);
c. geological data attesting to the presence of materials, their quality, and approximate quantity;
d. data relating to surface or groundwater and soil quality;
e. the land to be exploited as a priority and the planned exploitation stages;
f. the maximum anticipated depth and the exploitation methods;
g. the general circulation plan, the road sections for which participation from the owner and operator is envisaged. This participation is set at the cost of the works necessitated by increased use. It is due for improvement, maintenance, or repair works;
h. the method of material processing and the location of the necessary installations;
i. the particular precautions to be observed;
j. the exploitation program and its probable duration;
k. the foreseeable environmental impact and the necessary protection measures;
l. the future land use, suspended until the end of exploitation, and the restoration in accordance with this use;
m. the final state of the land and the restoration works.
1. The draft plan, if not prepared by the department, must be submitted to it prior to being presented for public inquiry.
1. The department may request additional documents and studies to be included in the public inquiry file, considering the scope of the extraction works and local specificities.
**1. When the project concerns the exploitation of a part of a deposit whose existence is proven and whose boundaries are known or easily determinable, the department may, on its own initiative or upon the proposal of the interested territorial municipality or municipalities, defer the public inquiry and require that an extraction plan project be established with a view to the development of the entire deposit or, on the contrary, restrict the perimeter if it appears excessively large.**
**2. Such a request may also be submitted by owners collectively holding more than one-fifth of the presumed surface area of the deposit.**
1. Preliminary Examination, the Water, Soil, and Sanitation Service [C] submits the draft plan to the municipalities of the concerned communes and gathers their determinations. The right of opposition of the municipality during the investigation is reserved. The draft is subjected to a thirty-day public inquiry in the communes whose territory is concerned, with Article 57 LATC [C] being applicable for the remainder.
2. At the conclusion of the inquiry, the municipality or municipalities transmit their observations and the oppositions to the Department of Security and the Environment, hereinafter: the department [H]. Articles 73 and 74 LATC apply analogously.
3. ...
1. Articles 7 to 12 are applicable in case of the resumption of operation of an abandoned quarry.
1. Any modification of the extraction plan, such as perimeter extension, deepening, changes in the planned extraction stages, relocation of installations, significant changes in the method of material processing, modification of the restoration or circulation plans, is subject to the same procedure as the adoption of the plan.
**1. No extraction work or preparatory work for extraction may begin until the department has issued the operating permit.**
1. The application for an operating permit is submitted to the department by the owner and the operator jointly.
2. The implementing regulation [G] specifies the contents of the application and sets out the list of annexed documents.
3. The department ensures that the measures taken for the operation comply with the requirements of the extraction plan.
4. If all the conditions governing extraction have been precisely defined in the plan, the application is not subject to public inquiry, and the granting of the operating permit is published in the Official Gazette of the Canton of Vaud. If this is not the case, or if the operation is not subject to an extraction plan, the application for an operating permit is subject to public inquiry according to the procedure provided in Articles 109 and following of the LATC [C]. Adjoining property owners and easement beneficiaries are personally notified by registered letter from the municipality. Elements already approved within the framework of the extraction plan cannot be subject to opposition.
1. Before issuing the permit, the department shall ensure, in particular
a. that the owner, operator, or one of their employees responsible for directing the operation possesses the necessary technical knowledge for managing the operation and complying with technical operating requirements;
b. that the operator has the machinery, equipment, and financial means necessary to operate the quarry at the established pace, in a rational manner and with due regard for the environment, as well as within reasonable timeframes;
c. that a geodesic engineer and, if necessary, a hydrogeologist, ensure the supervision of works within their respective specialisations;
d. that the owner and the operator have contracted insurance covering the risks arising from their civil liability;
e. that sufficient sureties are provided as guarantees for the obligations arising from Articles 26 to 28 of this Law.
1. The permit issued jointly to the owner and operator may be noted in the land register, which specifies the rights and obligations. It is automatically transferred by law to any new owner and to any new operator.
2. Any change of owner, operator, the person responsible for the operation, the surveyor, or the hydrogeologist must be immediately reported to the department, which verifies whether the conditions of Article 17 are met. Failing this, Articles 20 and 21 apply by analogy.
1. The department shall ensure the application of this law. It shall draw up and keep up to date the list of extraction plans and quarries subject to its supervision.
2. Its collaborators and representatives shall have free access at all times to the quarries and their installations.
3. The following are subject to special prior authorization from the department
a. the use of explosives;
b. measures relating to the discovery and use of topsoil outside the perimeter of the exploitation;
c. the relocation of installations;
d. the discovery or exploitation of a new stage.
1. The department may at any time order the owner and the operator to take the necessary measures to ensure compliance with the law, the extraction plan, or the operating permit; it may suspend operations that threaten to become a source of danger or are conducted in serious or repeated violation of the law, the plan, the permit, or the department's instructions.
2. Before making the decisions provided for in the preceding paragraph, the department may order an expert appraisal and require the owner or the operator to bear the costs, in whole or in part; except in cases of emergency, the department will hear from them beforehand.
3. If, upon the expiration of the specified period, the owner or operator does not take the required measures, the department may proceed with the necessary work; the costs shall be borne by the owner or the operator.
1. The permit may be revoked if the owner or operator seriously or repeatedly violates the obligations imposed by law, the extraction plan, the permit, or the competent authority.
1. The operator and the owner shall ensure that the quarry operation does not cause any damage to property belonging to the public domain or to private individuals, particularly public or private waters, whether harnessed or not, or to forests.
1. The operator ensures the safety of persons employed in the operation or authorized to enter the quarry.
1. The operator shall take the necessary measures to prevent third parties from accessing the quarry or its hazardous parts.
1. Articles 22 to 24 apply without prejudice to the rules governing the liability of the owner and the operator towards third parties or their personnel.
1. When, as a result of transportation related to the operation of the quarry, a public road is damaged or requires specific maintenance work, the owner and the operator must equitably share the costs of repair or maintenance. The permit specifies the sections on which compensation may eventually be due.
2. The amount of participation is determined by the department in charge of roads if it concerns a cantonal road, and by the municipality if it concerns a communal road.
1. The operator and the owner shall ensure that the operation of the quarry and the installations cause as little harm as possible to the appearance of the landscape and the surrounding areas; they are obliged to take all necessary measures to this end.
1. Upon the cessation of quarry operations, the owner and the operator must remove or relocate the installations and carry out the necessary work to restore the site in accordance with the provisions of the extraction plan and the operating permit; the department may require the land to be leveled, grassed, or afforested. The restoration should, as a general rule, be completed within one year. It may be required after the completion of a phase of operation.
2. The owner must ensure that, when the land is to return to agriculture or forestry, the soil has sufficient quality.
1. During operation, the department may require additional securities to guarantee the fulfillment of obligations arising from Articles 26 to 28.
1. Upon the termination of the operation, the department conducts an inspection of the compliant condition of the site restoration in the presence of the owner, the operator, the municipality, the immediate neighbors, and representatives of the relevant services. This inspection is published in the Official Gazette.
2. Thirty days after this publication, if no intervention has occurred, the owner and the operator are released from their obligations under this law and the securities are discharged.
3. Regulation [G] defines the terms of the publication.
1. Restrictions on the right of ownership arising from this law give rise to the payment of compensation when they amount to an expropriation.
2. The Expropriation Act [I] is applicable.
1. Offenses against the provisions of the present law are punishable by a fine of up to fifty thousand francs.
2. Prosecution shall proceed in accordance with the provisions of the law on the repression of offenses [J]; it is without prejudice to the obligation of the offender to restore the state existing prior to the violation of the legal provisions.
1. The following are subject to the present law
a. the exploitation of a new quarry;
b. the resumption of the exploitation of an abandoned quarry;
c. the modification or extension of the perimeter within which the exploitation of a quarry has been authorized.
2. For quarries whose application was submitted to public inquiry before the entry into force of the present law, the permit may be granted on the basis of the exception provided in Article 6, paragraph 2.
3. Furthermore, the provisions of Articles 13, 14, and 18 to 34 are applicable to quarries currently in operation.
1. Amendments related to the procedure for adopting decisions and classification plans are not applicable to the decisions and plans on which the Department of Security and the Environment and the Department of Infrastructure have already made determinations at the time this law comes into force.
1. The law of November 21, 1967, on careers is repealed.
1. The Council of State is entrusted with the execution of the present law. It shall publish the text in accordance with Article 27, number 2, of the Cantonal Constitution and shall set the date of its entry into force by decree.