Art. 5 REGULATION on the Energy Fund (RF-Ene) - Grant Conditions [ 2 ]

Chapter III
Open official source Full Act (19 Articles) Machine-readable Markdown (.md)

Art. 5 RF-Ene - Grant Conditions [ 2 ] · Grant Conditions [ 2 ]

1. The granting of aid must meet the following cumulative conditions

a. compliance with cantonal legislation, particularly the Subsidies Act [C];

b. compliance with the priorities defined by the State Council in energy policy, and specifically those mentioned in the Cantonal Energy Conception (hereinafter: the COCEN);

c. the submission of a complete and perfectly documented file, as well as the production of all technical and financial documents (budgets, accounts, plans, etc.) requested by the service and necessary for its evaluation.

← Art. 3 RF-Ene - Principle [ 2, 3 ] REGULATION on the Energy Fund (RF-Ene) - Constitution Art. 6 RF-Ene - Procedure [ 2 ] →

Need to analyze how this provision applies to your matter?

Cross-reference this statute against case law, commentaries, and related legislative provisions inside Legislator AI.

Open in Legislator →

Court Decisions Applying This Provision (1)

AC.2008.0304 · vd (art. 5 al. 1 let. a RF-Ene)
Solar Collector Subsidy Denial Upheld Due to Pre-Application Commencement of Work