Art. 5 LAW on Public Procurement (LMP-VD) - Subcontractors (art. 12 AIMP) · Subcontractors (art. 12 AIMP)

1. The tenderer shall indicate in its bid

a. the object and the share of the services to be subcontracted;

b. the company name and the registered office or establishment of the subcontractors.

2. Any change of subcontractor occurring during the performance of the contract must be based on valid grounds. The new subcontractor must possess the same skills and qualifications as the previously proposed subcontractor and meet the conditions of the tender. It must be announced in writing to the awarding authority for verification and approval before commencing the performance of its services.

3. The use of sub-subcontracting is prohibited.

4. Exceptionally, the awarding authority may authorise the use of sub-subcontracting when justified by technical, organisational or competence reasons, among others. In such a case, only recourse to a second level of subcontracting is permitted.

5. Failure to comply with any of the requirements set out in the preceding paragraphs constitutes grounds for exclusion of the tenderer or revocation of the award.

← Art. 4 Law on Public Procurement (LMP-VD) Act on Public Procurement (LMP-VD) - Purpose Art. 6 Public Procurement Law (PPL-VD) →

Need to analyze how this provision applies to your matter?

Cross-reference this statute against case law, commentaries, and related legislative provisions inside Legislator AI.

Open in Legislator →