721.31
LDE
CH-VD
Art. 7b Water Distribution Act (LDE) - c) Investigation and Approval Procedure for Principal Installations [ 3, 6 ]
Art. 7b LDE · c) Investigation and Approval Procedure for Principal Installations [ 3, 6 ]
1. Any project for the creation or transformation of main installations is subject to the approval of the department, after a thirty-day public inquiry in the territorial municipalities.
2. At the end of the inquiry, the concerned municipality or municipalities transmit the observations and objections to the department, which approves the project generally at the same time it decides on the objections.
3. With prior agreement from the department, the municipalities may waive the inquiry for matters of lesser importance.
Court Decisions Applying This Provision (1)
AC.2000.0037 · vd (art. 7b LDE)
Pipeline Replacement Servitude Dispute
The procedure for approving the water distribution system plan is discussed in relation to the applicability of LAT requirements, which forms the core of the substantive analysis for maintaining the administrative decision.