Article 110 Planning and Building Act (PBG) - Decision: Personal and Temporal Scope

Public Construction Law - Procedural Construction Law - Building Permit Procedure
Open official source Full Act (141 Articles) Machine-readable Markdown (.md)

Article 110 PBG · Decision: Personal and Temporal Scope

1. The building permit is transferable, provided it is not contingent upon proof of personal qualifications.

2. The building permit expires if construction work does not commence within one year from the finalization of the permit or if the construction work is interrupted for more than one year. This period is suspended for the duration of any civil litigation concerning the construction project.

3. For important reasons, the building authority can extend the building permit by a maximum of one year.

← Article 109 PBG Planning and Building Act (PBG) - Purpose and Subject Matter Article 111 PBG →

Need to analyze how this provision applies to your matter?

Cross-reference this statute against case law, commentaries, and related legislative provisions inside Legislator AI.

Open in Legislator →