1. The building permit is transferable, provided it is not contingent upon proof of personal qualifications.
2. The building permit expires if construction work does not commence within one year from the finalization of the permit or if the construction work is interrupted for more than one year. This period is suspended for the duration of any civil litigation concerning the construction project.
3. For important reasons, the building authority can extend the building permit by a maximum of one year.