Art. 3 Hydraulic Engineering Ordinance (WBV) - Submission
Art. 3 WBV - Submission · Submission
1. General Water Construction Projects must be submitted to the competent department and generally include the following documents
a. Project description along with plans;
b. Overview of the existing natural hazard situation, potential damages, and chosen protection objectives;
c. Overview of hydrology, geology, and vegetation;
d. Possible project variants with advantages and disadvantages;
e. Assessment of risk reduction;
f. Estimation of costs with a financing proposal;
g. Assessment of necessary agricultural and alpine measures in the catchment area;
h. Access infrastructure;
i. Sponsorship and stakeholders;
k. Priorities and timeline;
l. Affected protected areas;
m. Environmental impact report, if applicable;
n. Information on compatibility with guidelines and usage planning.
2. The competent department may request additional documents.