Art. 3 Hydraulic Engineering Ordinance (WBV) - Submission

Procedures – General Hydraulic Engineering Projects
Open official source Full Act (25 Articles) Machine-readable Markdown (.md)

Art. 3 WBV - Submission · Submission

1. General Water Construction Projects must be submitted to the competent department and generally include the following documents

a. Project description along with plans;

b. Overview of the existing natural hazard situation, potential damages, and chosen protection objectives;

c. Overview of hydrology, geology, and vegetation;

d. Possible project variants with advantages and disadvantages;

e. Assessment of risk reduction;

f. Estimation of costs with a financing proposal;

g. Assessment of necessary agricultural and alpine measures in the catchment area;

h. Access infrastructure;

i. Sponsorship and stakeholders;

k. Priorities and timeline;

l. Affected protected areas;

m. Environmental impact report, if applicable;

n. Information on compatibility with guidelines and usage planning.

2. The competent department may request additional documents.

← Art. 2 WBV - Consideration of the Principles Hydraulic Engineering Ordinance (WBV) - Governing Principles Art. 4 WBV - Approval and Cantonal Contribution →

Need to analyze how this provision applies to your matter?

Cross-reference this statute against case law, commentaries, and related legislative provisions inside Legislator AI.

Open in Legislator →