1. The Executive Management is the operational management body of the EWO. Its position, tasks, and powers are specifically determined by the Board of Directors in the Organizational Regulations.

← Art. 13 EWOG - b. Tasks Act on the Obwalden Electricity Works and Electricity Supply (EWOG) - Legal Form Art. 15 EWOG - Audit Office →

Need to analyze how this provision applies to your matter?

Cross-reference this statute against case law, commentaries, and related legislative provisions inside Legislator AI.

Open in Legislator →

Court Decisions Applying This Provision (2)

VVGE.1985.86.Nr.56 · ow (Art. 14 EWOG)
Electricity Connection Fee Disputes Subject to Public Law Decree, Not Lawsuit
Cited in the context of the legal nature of relationships between the electricity provider and consumers.
VVGE.1987.88.Nr.53 · ow (Art. 14 EWOG)
Electricity connection fee dispute regarding default interest and cost reimbursement
This provision requires government council approval for electricity tariffs set by the administrative board, which was discussed in relation to connection cost contributions.