Legislator Case Law & Legislation
720.0 BAUGLCLConstr CH-NE

Art. 37 Construction Law (LConstr.), March 25, 1996 - Duration of Validity

7 Public Works - Energy - Transport and Communications - 72 Construction - 720 General Provisions - CHAPTER 4 Control of Construction - Section 1: Building Permits
Open official source Full Act (75 Articles) Machine-readable Markdown (.md)

Art. 37 Construction Law (LConstr.), March 25, 1996 - Duration of Validity · Duration of Validity

[33] 1 The building permit becomes invalid if the execution of the project has not commenced within two years from the date it comes into effect or if it is interrupted for more than one year.

2. A project is considered to have commenced as soon as works, a change of use, or other measures outlined in the approved plans are executed, which on their own would require a building permit.

3. Exterior arrangements must be completed within one year from the end of the construction or installation works and in accordance with the approved plans.

4. The preliminary approval also becomes invalid if no application for final approval is submitted within two years of its coming into effect.

5. The validity of the building permit and the preliminary approval can be extended by up to two years for justifiable reasons and after consultation with the canton.

6. The building permit and the preliminary approval are personal; the Municipal Council may authorize a change of holder.

← Art. 36 Construction Law (LConstr.), March 25, 1996 - Two-Level Sanction 7 Public Works - Energy - Transport and Communications - 72 Constructions - 720 General Provisions - CHAPTER ONE General Provisions and Organization - Section 1: Purpose and Scope Art. 38 Law on Constructions (LConstr.), of March 25, 1996 - Simplified Procedure →

Need to analyze how this provision applies to your matter?

Cross-reference this statute against case law, commentaries, and related legislative provisions inside Legislator AI.

Open in Legislator →