Art. 9 Decree Regarding the Building Permit (DRBP)
Art. 9 Decree Regarding the Building Permit (DRBP)
1 Simplified Procedure as per Article 20 is applicable, subject to paragraph 3, to the following projects
a) small-scale buildings, work as defined by Article 4, paragraph 1, letter b, minor extensions of buildings or facilities;
b) significant modifications of buildings and facilities (Article 5);
c) constructions that are not permanently established (movable constructions);
d) modifications to the terrain.
2 The minor permit is granted by the municipal authority.
3 However, the minor permit procedure is excluded in the following cases
a) in case of construction or extension of buildings and facilities when construction costs exceed 100,000 francs;
b) when the project is related to another, to which the ordinary procedure applies, notably in case of demolition for the purpose of new construction;
c) when the concerned projects are contrary to the zoning designation;
d) when the project affects significant public interests, particularly those of nature protection, sites and heritage preservation, traffic safety, or local planning.
4 The minor permit procedure cannot be repeated with the intent to carry out a project that falls under the ordinary procedure.