Art. 21A Law on Construction and Spatial Planning (LCAT)
7. Constructions, travaux publics, énergie, Transportation and Communications » 70. Construction and Land Development » 701. Construction
Art. 21A Law on Construction and Spatial Planning (LCAT)
1 Once the application is complete and without waiting for publication, the competent authority for granting the building permit collects the special authorizations and opinions related to the project from the authorities involved in the procedure. These authorities must give their opinion within 30 days.
2 It ensures that the special authorizations and opinions are coordinated.
3 If the involved authorities issue contradictory opinions or if the competent authority for granting the building permit disagrees with the expressed opinions, the latter initiates a review of the concerned authorizations and opinions.