Legislator Case Law & Legislation
174.11 ÖBV-JUOMP-JU CH-JU

1. État, peuple, Authorities » 17. Authorities » 174. Public Procurement (ÖBV-JU)

30 Articles / Provisions · Switzerland · Canton of Jura
Open official source Machine-readable Markdown (.md)

Table of Provisions (30)

Art. premier Ordinance on Public Procurement (OMP-JU) Art. 2 Ordinance on Public Procurement (OMP-JU) Art. 3 Ordinance on Public Procurement (OMP-JU) Art. 4 Ordinance on Public Procurement (OMP-JU) Art. 5 Ordinance on Public Procurement (OMP-JU) Art. 6 Ordinance on Public Procurement (OMP-JU) Art. 7 Ordinance on Public Procurement (OMP-JU) Art. 8 Ordinance on Public Procurement (OMP-JU) Art. 9 Ordinance on Public Procurement (OMP-JU) Art. 10 Ordinance on Public Procurement (OPP-JU) Art. 11 Ordinance concerning Public Procurement (OMP-JU) Art. 12 Ordinance concerning Public Procurement (OMP-JU) Art. 13 Ordinance on Public Procurement (OMP-JU) Art. 14 Ordinance on Public Procurement (PPO-JU) Art. 15 Ordinance on Public Procurement (OMP-JU) Art. 16 Ordinance on Public Procurement (OMP-JU) Art. 17 Ordinance concerning Public Procurement (OMP-JU) Art. 18 Ordinance concerning Public Procurement (OMP-JU) Art. 19 Ordinance concerning Public Procurement (OMP-JU) Art. 20 Ordinance on Public Procurement (OMP-JU) Art. 21 Ordinance on Public Procurement (OMP-JU) Art. 22 Ordinance concerning Public Procurement (OMP-JU) Art. 23 Ordinance on Public Procurement (OPP-JU) Art. 24 Ordinance on Public Procurement (OPP-JU) Art. 25 Ordinance on Public Procurement (OMP-JU) Art. 26 Ordinance on Public Procurement (OMP-JU) Art. 27 Ordinance on Public Procurement (OMP-JU) Art. 28 Ordinance on Public Procurement (OMP-JU) Art. 29 Ordinance on Public Procurement (OMP-JU) Art. 30 Ordinance on Public Procurement (OMP-JU)

Statutory Text (30 Articles)

1. État, peuple, Authorities » 17. Authorities » 174. Public Procurement

1 This ordinance governs the implementing provisions of the Public Procurement Law (hereinafter: "PPL-JU").

2 Federal provisions regulating specific public procurements remain reserved, notably those concerning the construction and maintenance of national roads.

1. État, peuple, Authorities » 17. Authorities » 174. Public Procurement

The terms used in this ordinance to designate persons apply equally to women and men.

1. État, peuple, Authorities » 17. Authorities » 174. Public Procurement

1 The value of contracts concerning major construction works and finishing works not subject to international agreements is defined by all the services included in the Construction Cost Code (CCC) up to three digits.

2 The following CCCs are exempt from the requirement set forth in paragraph 1

a) CCC 211.1, 212.1, 213.1, 214.5, 215.1, 224.4, 225.0, 226.0, 227.0, 271.2, 282.7, 283.0, and 285.0 (external scaffolding);

b) CCC 281.0 (floor screeds);

c) CCC 281.6 (tiling);

d) CCC 281.7 (wooden floor coverings);

e) CCC 281.9 (skirting boards).

1. État, peuple, Authorities » 17. Authorities » 174. Public Procurement

1 In order to verify that the bidders meet the participation requirements and to assess their qualifications, the awarding body may specifically require certain documents mentioned in Annex 1 of this ordinance.

2 It selects and designates the evidence to be provided based on the nature and significance of the contract.

3 The awarding body may choose not to require the submission of the documents referred to in paragraph 1 within the framework of a direct award procedure as defined in Article 21, paragraph 1, of the Intercantonal Agreement on Public Procurement dated November 15, 2019 (hereinafter: "AIMP").

1. État, peuple, Authorities » 17. Authorities » 174. Public Procurement

1 The contractor notifies the adjudicator, by mail or email, when they employ temporary workers for the execution of a contract.

2 The notification must occur before the temporary workers are present at the place of execution.

3 Each time a new temporary worker is dispatched, the notification is repeated.

1. État, peuple, Authorities » 17. Authorities » 174. Public Procurement

No permanent lists of qualified bidders are maintained within the meaning of Article 14 LMP-JU.

1. État, peuple, Authorities » 17. Authorities » 174. Public Procurement

When the proper execution of a contract requires it, the awarding authority may require that bidder consortiums have a specific legal status before the award.

1. État, peuple, Authorities » 17. Authorities » 174. Public Procurement

In addition to the indications provided in Article 36 AIMP, the tender documents shall contain

a) the method of assessing the price;

b) the conditions for setting and applying the contractual penalty provided for in Article 13 LMP-JU;

c) the payment terms, including the required financial guarantees;

d) the deadline and procedures for obtaining additional information related to the tender documents (formal requirements, location, etc.).

1. État, peuple, Authorities » 17. Authorities » 174. Public Procurement

1 The adjudicator shall respond to questions related to the tender documents within seven days following the expiry of the deadline set in accordance with Article 8, letter d.

2 The information provided to one bidder must simultaneously be communicated to the other bidders, along with the questions posed, in anonymized form.

1. État, peuple, Authorities » 17. Authorities » 174. Public Procurement

1 As a general rule, the opening of tenders is not public.

2 In open procedures, the minutes of the opening of tenders are made available to all bidders within 10 days after the opening of the tenders.

1. État, peuple, Authorities » 17. Authorities » 174. Public Procurement

1 The documents provided by the bidders, particularly trade and manufacturing secrets, are treated confidentially.

2 The adjudicator may only use or transmit these documents to a third party with the consent of the respective bidders.

1. État, peuple, Authorities » 17. Authorities » 174. Public Procurement

The publication in the Official Journal of the various acts referred to in Article 48, paragraph 1, AIMP includes the following indications

a) the name and address of the adjudicator;

b) the type and purpose of the contract, including, where applicable, the indication of division into lots;

c) the type of procedure;

d) whether the contract is subject to international agreements;

e) in the case of invitations to tender, the deadline for submission of offers and the period during which they are valid;

f) in the case of award decisions, the name of the successful tenderer and the date of the award;

g) in the case of decisions to interrupt the procedure, the reasons leading to such a decision;

h) in the case of direct negotiations for contracts subject to international agreements, in addition to the indications provided for in subsection f, the condition set out in Article 21, paragraph 2, AIMP justifying recourse to such a procedure.

1. État, peuple, Authorities » 17. Authorities » 174. Public Procurement

1 The Department of the Environment (hereinafter: the Department) establishes the annual electronic statistics on markets subject to international agreements.

2 To this end, the contracting authorities collaborate with the Department and communicate the data related to their markets via the Internet platform for public procurement jointly operated by the Confederation and the cantons.

3 The Department transmits the annual statistics to the Intercantonal Public Procurement Authority for the attention of the State Secretariat for Economic Affairs.

1. État, peuple, Authorities » 17. Authorities » 174. Public Procurement

1 Parallel design competitions and assignments may be organized to acquire all types of services mentioned in Article 8, paragraph 2 of the AIMP. They are particularly used to find sustainable and innovative solutions.

2 The contracting authority has the discretion to organize competitions or parallel study assignments when the selection of a project requires a prior evaluation of various solutions, notably from a conceptual, aesthetic, ecological, economic, functional, or technical perspective.

1. État, peuple, Authorities » 17. Authorities » 174. Public Procurement

1 Parallel studies competitions or mandates may take one of the following forms

a) idea competitions or mandates;

b) project competitions or mandates;

c) competitions or mandates concerning studies and execution.

2 Competitions are organized for tasks that can be defined beforehand in a sufficient or exhaustive manner.

3 Parallel study mandates are organized for tasks that, due to their complexity, can only be specified and completed during the procedure and require a non-anonymous dialogue with the bidders.

1. État, peuple, Authorities » 17. Authorities » 174. Public Procurement

1. When their value reaches at least the threshold value specified in Annex 2 of the AIMP, competitions and parallel study mandates are organized according to the rules of the open or selective procedure.

2. When the threshold value specified in Annex 2 of the AIMP is not reached, competitions and parallel study mandates may be organized according to the invitation procedure.

3. The number of participants may be reduced during the procedure if this possibility has been mentioned in the competition program or parallel study mandates.

1. État, peuple, Authorities » 17. Authorities » 174. Public Procurement

**1 The Value of Competitions and Parallel Study Mandates Comprises:**

a) In the case of an ideas competition, the total sum of the prizes;

b) In the case of a project competition, the total sum of the prizes and the estimated value, excluding VAT, of the additional study services defined in the competition program;

c) In the case of a competition involving studies and implementation, the total sum of the prizes and the estimated value, excluding VAT, of the services that will be awarded as a result of the competition;

d) In the case of ideas mandates, the total sum of the lump-sum compensation paid to participants;

e) In the case of project mandates and mandates involving studies and implementation, the total sum of the compensation and the estimated value of the additional services defined in the parallel study mandates program, which will be awarded as a result of these processes.

**2** The adjudicator sets a reasonable amount for the total prizes. To do this, they take into account the sums of the prizes and mentions usually practiced, the type of competition, the services required from participants, the expected number of participants, any possible fixed compensations intended for participants, as well as the additional study services or the adjudication planned.

**3** The amount of the lump-sum compensation is determined based on an estimate of the costs for all the services that participants must provide in all the relevant areas to develop their proposals and is indicated in the parallel study mandates program.

1. État, peuple, Authorities » 17. Authorities » 174. Public Procurement

1 To prepare for the competition or parallel study mandates, the adjudicator may seek the advice of one or more external specialists.

2 These specialists may be part of the jury provided that they have not been tasked with the possible preliminary examination referred to in Article 21.

1. État, peuple, Authorities » 17. Authorities » 174. Public Procurement

1. The invitation to tender concerning a competition or parallel study contracts must include the information leading the interested parties to

a) request the program of the competition or parallel study contracts;

b) participate in the selection phase in the case of a selective procedure;

c) register in the case of an open procedure.

2. The notice of invitation to tender and the program of the competition or parallel study contracts contain at least the information mentioned in Annex 2 of this ordinance.

1. État, peuple, Authorities » 17. Authorities » 174. Public Procurement

**1 Participants in the competitions submit their proposals anonymously. If this condition is not met, they are excluded from the procedure.**

**2 The adjudicator ensures the anonymity of the proposals submitted by the participants in the competitions until the jury has evaluated and ranked them, awarded the prizes, and, if applicable, made a recommendation for the continuation of the procedure.**

**3 Anonymity must also be guaranteed during any subsequent refinement stage.**

1. État, peuple, Authorities » 17. Authorities » 174. Public Procurement

1 The adjudicator or a specialist appointed by the adjudicator may conduct a review of the proposals submitted by the participants before they are presented to the jury.

2 This preliminary review focuses on compliance with the requirements of the competition program or the parallel study mandates. Its result is recorded, without value judgment, in a report which is then communicated to the adjudicator and the jury.

1. État, peuple, Authorities » 17. Authorities » 174. Public Procurement

**1 The Jury Comprises:**

a) Qualified professionals in the fields related to the service subject to the competition or parallel study mandates;

b) Other members freely appointed by the adjudicator.

**2 The majority of the jury members must be composed of professionals, and at least half of them must be independent of the adjudicator.**

**3 The jury may seek the advice of one or more external specialists for the assessment of particular issues.**

1. État, peuple, Authorities » 17. Authorities » 174. Public Procurement

1 The jury has the following responsibilities

a) It approves the program of the competition or parallel study mandates;

b) It evaluates the proposals submitted by the participants;

c) It decides on the ranking and the awarding of prizes;

d) It issues a recommendation for the continuation of the procedure.

2 The jury may also award commendations if the maximum amount and conditions for these commendations are specified in the competition program or parallel study mandates.

1. État, peuple, Authorities » 17. Authorities » 174. Public Procurement

1 The jury ranks the participants' submissions that comply with the provisions of the competition program or the parallel study mandates and allocates the prizes or compensations. A first prize is always awarded. Tied prizes are not permitted.

2 Outstanding submissions, which have been excluded from prize or compensation allocation for violating the provisions of the competition program or the parallel study mandates, may receive honorable mentions.

3 The jury may include in its ranking the submissions that received honorable mentions, provided it decides unanimously and this possibility is mentioned in the competition program or the parallel study mandates.

1. État, peuple, Authorities » 17. Authorities » 174. Public Procurement

1 The contracting authority is in principle bound to follow the jury's recommendation.

2 However, the contracting authority can be released from this obligation by paying compensation in accordance with Article 27, paragraph 2, of this ordinance.

1. État, peuple, Authorities » 17. Authorities » 174. Public Procurement

1 In competitions or parallel study mandates, participants retain their copyright on the proposals they have submitted, unless the competition or parallel study mandate program provides otherwise.

2 All documents submitted by the participants become the property of the adjudicator.

1. État, peuple, Authorities » 17. Authorities » 174. Public Procurement

1 The winner of a competition or parallel study mandates

a) in the case of an ideas competition or mandates, is not entitled to be awarded additional services;

b) in the case of a project competition or mandates, may in principle claim the award of services defined in the competition program or parallel study mandates that the contracting authority decides to implement;

c) in the case of a competition or mandates concerning studies and implementation, may in principle claim the award of services defined in the competition program or parallel study mandates that the contracting authority decides to implement.

2 A compensation equal to one-third of the total amount of the prizes and honors must be paid

a) to the winner, when the contracting authority, contrary to the recommendations of the jury, awards a supplementary study mandate or contract to a third party;

b) to the author of a proposal, when the contracting authority uses it without awarding the supplementary study mandate to them.

3 The compensations are cumulative if both situations described in paragraph 2 occur during the same procedure.

4 If the contracting authority renounces, after the jury's verdict, to implement the project or to award a supplementary mandate or contract, the right to compensation as per paragraph 2 expires. If the contracting authority reconsiders its decision within ten years after the jury's verdict, the right to compensation as per paragraph 2 can be claimed again.

1. État, peuple, Authorities » 17. Authorities » 174. Public Procurement

1 The awarding authority communicates the jury's decision in writing to all participants.

2 It publishes the results of the competitions or parallel study mandates in an appropriate manner.

3 It presents the projects to the public upon the communication of the decision and the publication of the results.

1. État, peuple, Authorities » 17. Authorities » 174. Public Procurement

The ordinance of April 4, 2006, regarding the awarding of public contracts is repealed.

1. État, peuple, Authorities » 17. Authorities » 174. Public Procurement

This ordinance shall come into effect on May 1, 2024.

Need to analyze how this provision applies to your matter?

Cross-reference this statute against case law, commentaries, and related legislative provisions inside Legislator AI.

Open in Legislator →