The Republic and Canton of Jura adheres to the Intercantonal Agreement of November 15, 2019, on Public Procurement (IAAP).
It is published as an annex to this decree.
This agreement applies to the awarding of public contracts by the contracting authorities subject to it, whether or not these contracts are subject to international agreements.
Order of 9 September 1998 Approving the Intercantonal Agreement of 25 November 1994 on Public Procurement is Repealed.
The present agreement aims to achieve the following objectives
a) an economical use of public funds that has sustainable economic, ecological, and social effects;
b) transparency of tendering procedures;
c) equality of treatment and non-discrimination of bidders;
d) effective and fair competition among bidders, particularly through measures against unlawful agreements affecting competition and against corruption.
Intercantonal Agreement of November 25, 1994, on Public Procurement Remains Applicable to Cantons Not Adhering to the Intercantonal Agreement of November 15, 2019, on Public Procurement.
For the purposes of this agreement, the following definitions apply
a) Bidder: A natural or legal person, of private or public law, or a group of such persons that offers services or seeks to participate in a public tender or to be delegated a public task or granted a concession;
b) Public enterprise: An enterprise over which public authorities may exert direct or indirect dominant influence due to ownership, financial participation, or the rules that govern it; dominant influence is presumed when an enterprise is predominantly funded by the state or other public enterprises, when its management is subject to control by the state or other public enterprises, or when its administrative, managerial or supervisory body consists of members the majority of whom are appointed by the state or other public enterprises;
c) International agreements: The agreements from which Switzerland's international commitments regarding public contracts are derived;
d) Working conditions: The mandatory provisions of the Code of Obligations concerning employment contracts, the normative provisions contained in collective labor agreements and standard employment contracts or, lacking these, the usual working conditions in the region and industry;
e) Worker protection provisions: The provisions of public labor law, including the provisions of the Act on Labor of March 13, 1964, the implementing provisions thereof, and the provisions concerning accident prevention;
f) Public law body: Any body
- created specifically to meet needs of general interest having a non-commercial or industrial character,
- endowed with legal personality, and
- whose activity is either predominantly financed by the state, local authorities, or other public law bodies, or whose management is subject to control by these entities, or whose administrative, managerial or supervisory body consists of members more than half of whom are appointed by the state, local authorities, or other public law bodies;
g) Public authorities: The state, local authorities, public law institutions, and associations formed by one or more of these local authorities or one or more of these public law institutions.
This decree is subject to an optional referendum.
For contracts subject to international agreements, public authorities as well as central or decentralized administrative units, including public law entities from the canton, district, and municipality according to cantonal and communal law, are subject to the present agreement, except for their commercial or industrial activities.
For contracts subject to international agreements, the present agreement also applies to public authorities and public or private enterprises that provide a public service and benefit from exclusive or special rights, provided that they conduct activities in Switzerland in one of the sectors listed below
a) the provision or operation of fixed networks intended to provide a service to the public in the field of production, transportation, or distribution of drinking water or the supply of drinking water to these networks;
b) the provision or operation of fixed networks intended to provide a service to the public in the field of production, transportation, or distribution of electrical energy or the supply of electrical energy to these networks;
c) the operation of networks intended to provide a service to the public in the field of transport by urban rail, automated system, tramway, trolleybus, bus, or funicular;
d) the provision of airports or other transport terminals to air carriers;
e) the provision of inland ports or other transport terminals to river carriers;
f) the provision or operation of railways, including rail transport;
g) the provision or operation of fixed networks intended to provide a service to the public in the field of production, transportation, or distribution of gas or heat or the supply of gas or heat to these networks, or
h) the exploitation of a geographical area for the purpose of prospecting or extracting oil, gas, coal, or other solid fuels.
The adjudicating authorities mentioned in paragraph 2 are only subject to the present agreement if the acquisitions are made in the relevant field of activity and not in other fields of activity.
For contracts not subject to international agreements, the following are also subject to the present agreement
a) other entities performing cantonal or communal tasks to the extent that they do not have commercial or industrial activities;
b) projects and services that are subsidized by more than 50 percent of the total cost by public funds.
If a third party enters a public contract on behalf of one or more adjudicating authorities, it is subject to the present agreement in the same manner as the authorities it represents.
The Government sets the entry into force of this order.
If several contracting authorities subject to federal law and this agreement participate in a procurement process, the law of the entity bearing the majority of the financing applies. If the total cantonal share exceeds that of the Confederation, this agreement applies.
If several contracting authorities subject to this agreement jointly participate in a public procurement process, the law of the canton bearing the largest share of the financing applies.
If several contracting authorities participate in a procurement process, they have the option, by mutual agreement, to subject this process to the law of one of the contracting authorities, thereby deviating from the aforementioned principles.
A procurement process, the execution of which does not take place at the seat of the contracting authority, is subject to the law of the location of the contracting authority’s seat or the law of the main place of business.
A procurement process launched by a joint organization is subject to the law applicable at the location of the organization's seat. If it does not have one, the applicable law is that of the main place of business.
Public or private enterprises benefiting from exclusive or special rights granted by the Confederation or executing tasks in the national interest may choose to subject their procurements to the law applicable at their seat or to federal law.
Under the present agreement, Swiss bidders as well as bidders from states with which Switzerland has contractually committed to provide market access and which have reciprocated such commitments towards Switzerland, are authorized to submit a bid.
Foreign bidders are permitted to submit a bid for markets not subject to international agreements, provided they come from states granting reciprocity, or the awarding authority authorizes them to do so.
The Federal Council shall establish a list of states that have committed to giving Switzerland access to their markets. This list is periodically updated.
The cantons are authorized to conclude agreements with neighboring regions and states.
**When a Sectoral Market Mentioned in Article 4, Paragraph 2, is Subject to Effective Competition**
The Intercantonal Authority for Public Procurement (IAPP) may propose to the Federal Council to entirely or partially exempt the corresponding acquisitions from this agreement. Adjudicators active in the concerned sectoral market may submit a corresponding request to the IAPP.
An exemption applies to the corresponding acquisitions of all adjudicators active in the concerned sectoral market.
A public contract is an agreement concluded between a contracting authority and a bidder with the aim of performing a public task. It is characterized by its onerous nature as well as by the exchange of performances and counter-performances, with the characteristic performance being provided by the bidder.
The following types of performances are distinguished
a) construction works (structural work and finishing work);
b) supplies;
c) services.
Mixed contracts are composed of different types of performances as mentioned in paragraph 2 and form a comprehensive contract. The qualification of the latter is determined by the type of performance whose value is the greatest.
Performances cannot be combined or grouped with the intention or effect of circumventing the provisions of this agreement.
The delegation of a public task or the granting of a concession is considered a public contract when the bidder is granted, through such delegation or granting, exclusive or special rights that they exercise in the public interest in exchange for compensation or indemnity, whether direct or indirect. The provisions of special laws under federal and cantonal law remain reserved.
This Agreement does not apply to
a) the acquisition of services intended to be sold or resold in commerce or to be used in the production or provision of services intended for sale or resale in commerce;
b) the acquisition, leasing, or renting of buildings, structures, or facilities, nor to the rights pertaining thereto;
c) the payment of financial aid;
d) contracts concerning financial services related to the issuance, purchase, sale, transfer, or management of securities or other financial instruments, or services provided by central banks;
e) contracts with institutions for the handicapped, socio-professional integration organizations, charitable organizations, or penitentiary institutions;
f) contracts governed by personnel law;
g) provident institutions of public law in cantons and communes.
This Agreement also does not apply to the acquisition of services
a) from bidders who hold an exclusive right to provide these services;
b) from other legally independent contracting authorities subject to public procurement law that are not in competition with private bidders for the provision of these services;
c) from organizational units dependent on the contracting authority;
d) from bidders over whom the contracting authority exercises control equivalent to that which it exercises over its own services and who provide the majority of their services to the contracting authority.
Public contracts are also not subject to this Agreement
a) where exemption is deemed necessary for the protection and maintenance of external or internal security or public order;
b) where exemption is deemed necessary for the protection of the health or life of persons or for the protection of wildlife and flora;
c) where the initiation of a call for tenders would infringe upon intellectual property rights.
During the awarding of public contracts, the contracting authority shall observe the following principles
a) it acts in a transparent, objective, and impartial manner;
b) it takes measures against conflicts of interest, unlawful agreements affecting competition, and corruption;
c) it ensures equal treatment of bidders in all phases of the procedure;
d) it does not engage in price negotiations;
e) it commits to maintaining the confidentiality of information provided by bidders.
**Public Procurement Contracts**
Public procurement contracts concerning services to be performed in Switzerland are awarded only to bidders who comply with the provisions relating to worker protection and the working conditions in force in Switzerland, the obligations regarding notification and authorization mentioned in the Law of June 17, 2005, on Undeclared Work (LTN), as well as the provisions relating to equal pay treatment between women and men.
Public procurement contracts concerning services to be performed abroad are awarded only to bidders who comply at least with the fundamental conventions of the International Labour Organization (ILO) mentioned in Annex 3. Additionally, the awarding authority may require compliance with other important international labor standards and the provision of corresponding evidence, as well as agreeing on the implementation of inspections.
A public procurement contract can only be awarded to bidders who comply at least with the legal requirements relating to environmental protection and the conservation of natural resources in force at the location of the service; these requirements include, in Switzerland, the provisions of Swiss environmental law and, abroad, the international environmental protection conventions determined by the Federal Council and mentioned in Annex 4.
Subcontractors are required to comply with the requirements defined in paragraphs 1 to 3. This obligation must be mentioned in the agreements that the bidders conclude with their subcontractors.
The awarding authority may verify compliance with the requirements defined in paragraphs 1 to 3 or delegate this competence to third parties, unless this verification has been entrusted to an authority instituted by a special law or to another competent body, in particular, a joint control body. For the purposes of these verifications, the awarding authority may provide the competent authority or control body with the necessary information and make documents available to them. Upon request, the bidder must produce the required evidence.
The control body or the authority in charge of verifying compliance with the requirements defined in paragraphs 1 to 3 inform the awarding authority of the results of their verifications and any measures taken.
Shall not participate in the tendering procedure, on behalf of the awarding authority or the jury, individuals who
a) have a personal interest in the contract;
b) are related by marriage or registered partnership or are actually living as a couple with a bidder or a member of one of its bodies;
c) are relatives by blood or marriage, directly or up to the third degree in collateral line, of a bidder or a member of one of its bodies;
d) represent a bidder or have acted in the same matter for a bidder, or
e) for any other reason, do not have the necessary independence to participate in the awarding of public contracts.
The request for disqualification must be submitted immediately after the reason for disqualification is known.
The awarding authority or the jury rules on disqualification requests in the absence of the person concerned.
The awarding authority may specify in the call for tenders that bidders who have a relationship with a jury member that justifies disqualification in competitions and parallel study mandates shall be excluded from the procedure.
Bidders who have participated in the preparation of a procurement procedure are not allowed to submit a bid when the competitive advantage thus gained cannot be offset by appropriate means and the exclusion does not compromise effective competition among bidders.
The appropriate means to offset a competitive advantage include in particular
a) the provision of all essential information regarding the preliminary work;
b) the disclosure of the names of participants involved in the preparation of the contract;
c) the extension of minimum deadlines.
A market study required by the contracting authority before the call for tenders does not result in the preclusion of the commissioned bidders. The contracting authority publishes the results of the market study in the tender documents.
### The Awarding Authority Estimates the Probable Value of the Contract
A public contract cannot be subdivided to circumvent the provisions of this agreement.
For the estimation of the value of a contract, all the services to be awarded or remunerations that are closely related from a material or legal perspective must be taken into account. All elements of remuneration are considered, including those related to the options for extension and options concerning supplementary contracts, as well as all expected bonuses, fees, commissions, and interests, excluding value-added tax.
For contracts of a definite duration, the value of the contract is calculated by adding the remunerations to be paid over the entire duration of the contract, including remunerations linked to any extension options. The duration of these contracts generally cannot exceed five years. In duly justified cases, a longer duration may be provided.
For contracts of an indefinite duration, the value of the contract is calculated by multiplying the monthly remuneration by 48.
For contracts concerning periodically necessary services, the value of the contract is calculated based on the remuneration that was paid for such services during the previous twelve months or based on an estimate of needs over the twelve months following the first order.
**The procedure is chosen based on the value of the contract and the threshold values indicated in Annexes 1 and 2. After consulting the Federal Council, the AiMp periodically adjusts the threshold values according to international commitments.**
The Confederation ensures the participation of the cantons in any renegotiation of international commitments related to the threshold values.
When the total value of several construction works referred to in Annex 1, item 1, which are necessary for the completion of the same project, reaches the threshold value determining the application of international agreements, the provisions of this agreement that govern contracts subject to international agreements apply. Conversely, when these construction works each have a value less than 2 million francs and their cumulative value does not exceed 20% of the total value of the project, they are subject to the provisions of this agreement that govern contracts not subject to international agreements (de minimis clause).
For construction works not subject to international agreements, the applicable procedure is determined based on the value of each individual work.
Depending on its value and the threshold values, a public contract may, at the discretion of the awarding authority, be awarded through an open procedure, a selective procedure, an invitation procedure, or a negotiated procedure.
**In the Open Procedure**
In the open procedure, the awarding authority issues a public call for tenders for the contract. Any bidder may submit a tender.
In the selective procedure, the contracting authority issues a public call for tenders for the contract, inviting bidders to initially submit a request to participate.
The contracting authority selects the bidders allowed to submit a bid based on their qualifications.
The contracting authority may limit the number of bidders allowed to submit a bid, provided that effective competition is still guaranteed. If possible, it authorizes at least three bidders to submit a bid.
**Invitation Procedure**
The invitation procedure is applicable to public contracts not subject to international agreements and that reach the threshold values indicated in Annex 2.
In the invitation procedure, the adjudicating authority invites selected bidders to submit an offer, without issuing a public call for tenders. For this purpose, the authority prepares tender documents. If possible, at least three offers are requested.
In the negotiated procedure, the contracting authority awards a public contract directly to a bidder without initiating a call for tenders. It may request offers for the purpose of comparison and conduct negotiations.
The contracting authority may award a negotiated contract without consideration of the threshold values when one of the following conditions is met
a) no offer or request to participate is submitted under the open, selective, or invited procedure, no offer meets the essential requirements of the call for tenders or complies with the technical specifications, or no bidder meets the eligibility criteria;
b) there is sufficient evidence to suggest that all offers submitted under the open, selective, or invited procedure result from an illegal agreement affecting competition;
c) only one bidder is considered due to the technical or artistic characteristics of the contract or for reasons of intellectual property protection, and there is no suitable alternative solution;
d) due to unforeseen events, the urgency of the contract is such that, even by shortening deadlines, an open, selective, or invited procedure cannot be completed;
e) a change of bidder for services intended to replace, complement, or increase services already provided is not possible for economic or technical reasons or would cause significant difficulties or a substantial increase in costs;
f) the contracting authority purchases new goods (prototypes) or services of a new kind that have been produced or developed at its request under a research, experimentation, study, or original development contract;
g) the contracting authority purchases services on a commodity market;
h) the contracting authority can purchase services at a significantly lower price than usual prices due to a time-limited advantageous offer (notably in the case of liquidations);
i) the contracting authority awards the supplementary contract to the winner of a study competition or a competition concerning studies and execution, or to the winner of a selection procedure linked to study mandates or mandates concerning studies and execution; the following conditions must be met
1. the previous procedure was organized in compliance with the principles of this agreement,
2. the proposed solutions were evaluated by an independent jury,
3. the contracting authority reserved in the call for tenders the right to award the supplementary contract through a negotiated procedure.
For each contract awarded by negotiation under paragraph 2, the contracting authority establishes documentation indicating
a) the names of the contracting authority and the selected bidder;
b) the nature and value of the purchased service;
c) the circumstances and conditions justifying the use of the negotiated procedure.
The awarding authority organizing a design competition or a competition involving design and implementation, or awarding parallel study assignments, defines the procedure on a case-by-case basis, in accordance with the principles set forth in this agreement. It may refer to the rules established in this area by professional associations.
The contracting authority may resort to an electronic auction to procure standardized services as part of a procedure governed by this agreement. An electronic auction is a process that may involve several stages during which bids are revised after a full evaluation and then re-ranked using electronic means. The intention to use an electronic auction must be mentioned in the call for tenders.
The electronic auction concerns
a) prices, when the contract is awarded to the bidder presenting the offer with the lowest total price, or
b) prices and values of other quantifiable elements of the offer (such as weight, degree of purity, or quality), when the contract is awarded to the bidder presenting the most advantageous offer.
The contracting authority verifies that the bidders meet the eligibility criteria and that the offers comply with the technical specifications. It proceeds to an initial evaluation of the offers based on the award criteria and their respective weighting. Before the auction begins, it communicates to each bidder
a) the method of automatic evaluation, including the mathematical formula, which is based on the specified award criteria;
b) the result of the initial evaluation of their offer, and
c) all other relevant information concerning the conduct of the auction.
All bidders admitted to participate in the auction are invited simultaneously, by electronic means, to submit a new or modified offer. The contracting authority may limit the number of bidders admitted, provided this intention was mentioned in the call for tenders or in the tender documents.
The electronic auction may comprise several stages. At the end of each stage, the contracting authority informs the bidders of their position in the ranking.
During an open or selective procurement procedure involving a complex contract, intellectual services, or innovative services, the contracting authority may engage in a dialogue with the bidders aimed at defining the purpose of the contract and developing and determining the applicable solutions or methods.
The intention to conduct a dialogue must be mentioned in the invitation to tender. The dialogue cannot be conducted with the aim of negotiating prices and total prices.
The contracting authority specifies its needs and requirements in the invitation to tender or in the tender documents. It also indicates
a) the conduct of the dialogue;
b) the possible content of the dialogue;
c) whether and, if so, how the bidders will be compensated for their participation in the dialogue and for the use of their intellectual property rights, their knowledge, and their experience;
d) the deadlines and terms for submitting the final offer.
The contracting authority may reduce the number of bidders participating in the dialogue based on objective and transparent criteria.
It records the conduct and content of the dialogue in an appropriate and understandable manner.
**The Contracting Authority May Launch a Call for Tenders for Contracts**
The contracting authority may launch a call for tenders for contracts that will be concluded with one or more bidders, with the aim of setting the conditions under which the required services will be acquired over a given period, particularly with regard to price and, where applicable, the estimated quantities. During the term of such a framework agreement, the contracting authority may enter into subsequent contracts based on it.
Framework agreements cannot be concluded with the intention or effect of preventing or eliminating competition.
The duration of a framework agreement may not exceed five years. Automatic renewal is not possible. A longer duration may be provided for in duly justified cases.
When a framework agreement is concluded with a single bidder, subsequent contracts are concluded in accordance with the conditions set out in this framework agreement. The contracting authority may request in writing that the contractual partner supplement their offer for the conclusion of subsequent contracts.
When framework agreements are concluded with multiple bidders for sufficient reasons, the contracting authority may conclude subsequent contracts either under the conditions set out in the relevant framework agreement, without a new invitation to tender, or according to the following procedure
a) before concluding a subsequent contract, the contracting authority consults the contractual partners in writing and informs them of its specific needs;
b) the contracting authority sets an appropriate deadline for the contractual partners to submit offers for the relevant subsequent contract;
c) offers must be submitted in writing and bind the bidder for the duration specified in the request for offers;
d) the contracting authority concludes the subsequent contract with the contractual partner who presents the offer judged to be the best based on the criteria defined in the tender documents or in the framework agreement.
During the bidding process and the execution of the awarded contract, the awarding authority ensures that the bidders and their subcontractors meet the participation conditions, particularly compliance with the requirements defined in Article 12, that they have paid the due taxes and social contributions, and that they do not enter into unlawful agreements affecting competition.
The awarding authority may require bidders to prove compliance with the participation conditions, particularly through a declaration or their registration on a list.
It specifies in the call for tenders or in the tender documents which proofs must be submitted and when.
**The Procuring Entity**
The procuring entity comprehensively defines, in the invitation to tender or in the tender documents, the eligibility criteria that bidders must meet. These criteria must be objectively necessary and verifiable for the relevant contract.
The eligibility criteria may particularly concern the professional, financial, economic, technical, and organizational capacities of the bidders, as well as their experience.
The procuring entity specifies in the invitation to tender or in the tender documents what evidence the bidders must provide and at what stage.
It cannot stipulate as a condition that the bidders have previously obtained one or more public contracts from a procuring entity subject to this agreement.
The awarding authority or the competent authority under the law may maintain a list of bidders who have the required aptitude to be eligible for public contracts.
The following information must be published on the internet platform of the Confederation and the cantons
a) source of the list;
b) information on the criteria to be met;
c) methods of verification and conditions for registration on the list;
d) validity period and procedure for renewing the registration.
A transparent procedure must ensure that it is possible at any time to submit a registration application, examine or verify a bidder's aptitude, as well as to register a bidder on the list or to remove them from it.
Bidders who are not listed are also allowed to participate in a procurement procedure, provided they demonstrate their aptitude.
The awarding authority evaluates the tenders based on award criteria related to the services. In addition to price and quality of the service, it may notably consider criteria such as suitability, timelines, technical value, cost-effectiveness, life cycle costs, aesthetics, sustainability, the plausibility of the offer, creativity, after-sales service, delivery conditions, infrastructure, innovativeness, functionality, customer service, technical skills, and method efficiency.
For contracts not subject to international agreements, the awarding authority may additionally take into account the extent to which bidders offer initial vocational training places, jobs for older workers, or reintegration for long-term unemployed individuals.
The awarding authority specifies the award criteria and their weighting in the call for tenders or in the tender documents. It may forgo indicating the weighting when the contract involves solutions, proposals for solutions, or procedures.
Standardized services may be awarded based solely on the lowest price criterion.
The contracting authority sets out the necessary technical specifications in the call for tenders or in the tender documents. These define the characteristics of the subject matter of the contract, such as its function, performance, quality, safety, dimensions, or production processes, and establish requirements relating to marking or packaging.
As far as possible and appropriate, the contracting authority sets the technical specifications based on international standards or, in their absence, on technical requirements applied in Switzerland, recognized national standards, or industry recommendations.
Specific trade names, brands, patents, copyrights, designs, types, origins, or particular producers cannot be required unless there is no other sufficiently precise or intelligible way to describe the subject matter of the contract, and provided that the contracting authority uses terms such as "or equivalent" in the tender documents. The burden of proving equivalence rests with the bidder.
The contracting authority may establish technical specifications that aim to conserve natural resources or protect the environment.
The participation of bidding consortia and the use of subcontractors are permitted, unless the awarding authority limits or excludes these possibilities in the call for tenders or in the tender documents.
Multiple participation of subcontractors or multiple participation of bidders in bidding consortia is only possible if expressly permitted in the call for tenders or in the tender documents.
The characteristic service must, in principle, be provided by the bidder.
The bidder must submit a comprehensive offer for the subject matter of the contract.
The awarding authority may divide the subject matter of the contract into several lots and award these to one or more bidders.
When the awarding authority has established lots, bidders may submit an offer for multiple lots, unless the awarding authority has provided other terms in the call for tenders. The awarding authority may limit the number of lots that can be awarded to a single bidder.
The awarding authority that reserves the right to require bidders to collaborate with third parties must indicate this in the call for tenders.
It may reserve, in the call for tenders, the right to award partial services.
The bidder is free to propose, in addition to their offer for the service described in the call for tenders, alternatives. The awarding authority may limit or exclude this possibility in the call for tenders.
An alternative is understood as an offer that allows achieving the market's objective in a manner different from that envisaged by the awarding authority.
Offers and requests for participation must be submitted in writing, completely and within the set deadlines, in accordance with the instructions provided in the call for tenders or in the tender documents. They may be submitted electronically when this option is provided in the call for tenders or in the tender documents and when the requirements set by the adjudicator are met.
**The call for tenders contains at a minimum the following indications:**
a) the name and address of the contracting authority;
b) the type of contract, the type of procedure, the corresponding CPV code and, additionally for services, the corresponding CPC code;
c) the description of the services, including the type and quantity, or where the quantity is unknown, the estimated quantity, as well as any options;
d) the place and deadline for the execution of the service;
e) where applicable, the division into lots, the limitation on the number of lots, and the possibility to submit partial bids;
f) where applicable, the limitation or exclusion of participation of bidding communities and the use of subcontractors;
g) where applicable, the limitation or exclusion of variants;
h) for services required periodically, if possible, the deadline for publishing the next call for tenders and, where applicable, the indication regarding the reduction of the deadline for submission of bids;
i) where applicable, the indication that there will be an electronic auction;
j) where applicable, the intention to conduct a dialogue;
k) the deadline for the submission of bids or requests to participate;
l) the formal requirements applicable to the submission of bids or requests to participate, including, where applicable, the indication that the service and price must be proposed in two separate envelopes;
m) the language(s) of the procedure and of the bids;
n) the eligibility criteria and required proofs;
o) where applicable, the maximum number of bidders who, within a selective procedure, will be invited to submit an offer;
p) the award criteria and their weighting, where these indications are not included in the tender documents;
q) where applicable, the reserved right to award partial services;
r) the duration of the validity of the offers;
s) the address where the tender documents can be obtained and, where applicable, a fee covering the costs;
t) the indication whether the contract is subject to international agreements or not;
u) where applicable, the pre-involved and admitted bidders to the procedure;
v) the legal remedies.
### The Tender Documents Must Contain the Following Indications, Unless Already Included in the Call for Tenders
a) The name and address of the contracting authority;
b) The subject of the contract, including technical specifications and certificates of compliance, plans, drawings, and necessary instructions, as well as indications regarding the required quantities;
c) Form requirements, conditions for participation in the award procedure, including the list of information and documents that bidders must provide in relation to these conditions, and any weighting of eligibility criteria;
d) The award criteria and their weighting;
e) When the contracting authority awards the contract electronically, any requirements relating to the authentication and encryption of information communicated electronically;
f) When the contracting authority provides for an electronic auction, the applicable rules, including the elements of the offer that may be modified and that will be evaluated based on the award criteria;
g) The date, time, and place of the opening of the offers, in case of public opening of the offers;
h) All other terms and conditions necessary for the submission of offers, particularly the currency in which they must be presented (as a rule, the Swiss franc);
i) The deadlines for the execution of services.
In open, selective, or invited procedures, all bids submitted within the allotted time are opened by at least two representatives of the awarding authority.
A report is drafted upon the opening of the bids. It must include at minimum the names of the persons present, the names of the bidders, the date of bid submission, any possible variants, as well as the total price of each bid.
When the service and the price must be proposed in two separate envelopes, the opening of the envelopes is governed by paragraphs 1 and 2, but only the total prices must be indicated in the report for the opening of the second envelopes.
The report is made accessible upon request to all bidders no later than after the award decision.
The awarding authority verifies whether the submitted bids comply with the formal requirements. Obvious calculation errors are corrected automatically.
The awarding authority may request bidders to provide explanations regarding their bids. It documents the questions asked and the answers received.
If the awarding authority receives a bid with an abnormally low price compared to the prices of other bids, it must request relevant information from the bidder to ensure that the participation conditions are met and that the other requirements of the call for tenders have been understood.
When the service and the price must be proposed in two separate envelopes, the awarding authority first establishes the list of the best offers from a qualitative point of view. In a second step, it evaluates the total prices.
In order to determine the most advantageous offer, the contracting authority may, in collaboration with the tenderers, rectify the tenders concerning the services and the terms of their execution.
A rectification is only carried out if
a) it is essential to clarify the object of the contract or the tenders, or to make the tenders objectively comparable based on the award criteria, or
b) modifications to the services are objectively and materially necessary; in this case, however, the subject matter of the contract, the criteria, and the specifications may not be adapted in such a way that the characteristic service or the circle of potential tenderers is altered.
A price adjustment may only be requested as part of a rectification carried out for one of the reasons mentioned in paragraph 2.
The contracting authority records the results of the rectification of tenders in minutes.
If the eligibility criteria are met and the technical specifications are complied with, the bids are examined and evaluated based on the award criteria in an objective, consistent, and traceable manner. The awarding authority prepares a report on the evaluation.
When a thorough examination and evaluation of the bids require considerable resources and provided it was announced in the call for tenders, the awarding authority may conduct a preliminary review of all proposals based on the submitted documents and rank them. It then selects, if possible, the three highest-ranked bids and subjects them to a detailed examination and evaluation.
The contract is awarded to the bidder who has submitted the most advantageous offer.
The contract may be concluded with the successful bidder after the expiration of the appeal period against the award, unless the Cantonal Administrative Court has granted suspensive effect to an appeal lodged against the award.
When an appeal procedure against the award is pending without suspensive effect being requested or granted, the adjudicator shall immediately inform the court of the conclusion of the contract.
**The Contracting Authority May Interrupt the Award Procedure Under the Following Circumstances:**
a) It decides, for sufficient reasons, to abandon the public procurement;
b) No bid meets the technical specifications or other requirements;
c) Due to changes in the general conditions, more advantageous bids are expected;
d) The bids submitted do not allow for an economical acquisition or clearly exceed the budget;
e) There is sufficient evidence of an illicit agreement affecting competition among bidders;
f) A significant modification of the required services is necessary.
In the event of a justified interruption of the procedure, bidders are not entitled to compensation.
The awarding authority may exclude a bidder from the award procedure, remove them from a list, or revoke an award if it is found that the bidder, one of its bodies, a third party it engages, or a body of the latter
a) does not or no longer meets the conditions for participation in the award procedure or has behavior that compromises the conformity of the procedure with legal provisions;
b) submits a bid or request to participate that is flawed with significant formal defects or substantially deviates from the requirements set in the call for tenders;
c) has been conclusively convicted for an offense committed to the detriment of the awarding authority in question or for a crime;
d) is subject to seizure or bankruptcy proceedings;
e) has violated provisions related to combating corruption;
f) refuses to comply with ordered checks;
g) does not pay due taxes or social security contributions;
h) has not correctly executed previous public contracts or has otherwise proven to be an unreliable partner;
i) has participated in the preparation of the contract, without being able to offset the resulting competitive disadvantage for other bidders by appropriate means;
j) has been excluded from future public contracts pursuant to Article 45, paragraph 1, which has come into force.
The awarding authority may also take the measures mentioned in paragraph 1 when sufficient indications suggest, particularly that the bidder, one of its bodies, a third party it engages, or a body of the latter
a) has provided false or misleading information to the awarding authority;
b) has entered into an illegal agreement affecting competition;
c) submits an abnormally low bid, without proving, after being invited to, that it meets the conditions of participation, and provides no assurance that the services to be contracted will be executed in accordance with the contract;
d) has violated recognized professional rules or damaged its professional honor or integrity through its actions or omissions;
e) is insolvent;
f) does not comply with provisions related to worker protection, working conditions, provisions relating to equal pay between women and men, confidentiality provisions, Swiss environmental law provisions, or international environmental protection agreements determined by the Federal Council;
g) has violated the reporting and authorization obligations mentioned in the LTN;
h) violates the Federal Law of 19 December 1986 against Unfair Competition.
When a bidder or subcontractor is found, either themselves or through their entities, in one or more of the situations listed in Article 44, paragraph 1, letters c and e, and paragraph 2, letters b, f and g, and when the act(s) in question are serious, they may be excluded for a maximum duration of five years from future contracts or may face a fine of up to 10% of the final offer price, either by the contracting authority or by the competent authority under the law. In cases of lesser severity, a warning may be issued.
These sanctions can be imposed independently of the application of other legal measures against the bidder, the subcontractor, or their culpable entities. If the contracting authority or competent authority under the law suspects an unlawful agreement affecting competition in the sense of Article 44, paragraph 2, letter b, it must inform the Competition Commission.
The contracting authority or competent authority under the law must announce to the AiMp the exclusions that have come into force issued based on paragraph 1. The AiMp maintains a non-public list of sanctioned bidders and subcontractors, which details the reason and duration of exclusion from public markets. It ensures that any contracting authority can access the data related to a specific bidder or subcontractor. For this purpose, it may establish an online data consultation procedure. The Confederation and the cantons mutually grant each other access to all information collected based on the present article. Upon the expiration of the sanction, the related entry is deleted from the list.
When a contracting authority contravenes the present agreement, the competent authority under the law issues appropriate instructions and ensures compliance with them.
When financial contributions are allocated for a public contract, they may be withdrawn in whole or in part or subject to a restitution request in the event of a violation of the present agreement by the contracting authority.
The awarding authority sets the deadlines for submitting tenders or requests to participate by considering the complexity of the market, the probable number of sub-contracting agreements, as well as the means of submission of tenders or requests to participate.
For contracts subject to international agreements, the following minimum deadlines apply
a) in the open procedure, 40 days from the publication of the call for tenders for the submission of tenders;
b) in the selective procedure, 25 days from the publication of the call for tenders for the submission of requests to participate and 40 days from the invitation to submit a tender for the submission of tenders.
An extension of these deadlines must be announced in a timely manner to all bidders or be published.
For contracts not subject to international agreements, the deadline for tender submission is generally at least 20 days. In the case of largely standardized services, it can be reduced to a minimum of 5 days.
In the event of a duly established emergency, the adjudicator may reduce the minimum time limits referred to in Article 46, paragraph 2, to a minimum of 10 days. The adjudicator may reduce the minimum deadline for submission of bids of 40 days set forth in Article 46, paragraph 2, by 5 days for each fulfilled condition when
a) the call for tenders is published electronically;
b) the tender documents are published simultaneously by electronic means;
c) bids submitted electronically are accepted.
The adjudicator may reduce the minimum deadline for submission of bids of 40 days set forth in Article 46, paragraph 2, to a minimum of 10 days when it has published, at least 40 days and at most 12 months before the publication of the call for tenders, a prior notice indicating
a) the subject of the contemplated contract;
b) the approximate deadline for submission of bids or requests to participate;
c) the fact that interested bidders should express their interest in the contract to the adjudicator;
d) the address at which the tender documents can be obtained;
e) all other indications listed in Article 35 which are already available at that date.
The adjudicator may reduce the minimum deadline for submission of bids of 40 days set forth in Article 46, paragraph 2, to a minimum of 10 days when acquiring periodically necessary services and has announced this reduction in a previous call for tenders.
Moreover, when the adjudicator purchases commercial goods or services or a combination of both, in any case, they may reduce the deadline for submission of bids to a minimum of 13 days, provided that the call for tenders and the tender documents are published simultaneously electronically. Furthermore, if the adjudicator agrees to receive bids for commercial goods or services electronically, they may reduce the deadline for submission of bids to a minimum of 10 days.
In open or selective procedures, the awarding authority publishes the prior notice, the call for tenders, the award, and the interruption of the procedure on an Internet platform for public procurement jointly operated by the Confederation and the cantons. It also publishes direct awards of contracts subject to international agreements.
Tender documents are generally made available at the same time and electronically. Access to these publications is free of charge.
The organization commissioned by the Confederation and the cantons to develop and operate the Internet platform may charge fees or dues from awarding authorities, bidders, and other persons using the platform or associated services. The amounts collected are determined by the number of publications or the extent of services provided.
When the call for tenders for a contract subject to international agreements is not published in one of the official languages of the World Trade Organization (WTO), the awarding authority simultaneously publishes a summary in one of the official WTO languages. This summary must at a minimum mention
a) the subject of the contract;
b) the deadline for submission of bids or requests to participate;
c) the address where the tender documents can be obtained.
For contracts not subject to international agreements, consideration should be given to the language of the location where the contract will be executed.
Awards of contracts subject to international agreements must, in principle, be published within a period of 30 days. The notice contains the following information
a) the type of procedure used;
b) the subject and scope of the contract;
c) the name and address of the awarding authority;
d) the date of the award;
e) the name and address of the successful bidder;
f) the total price of the winning bid, including value-added tax.
Cantons may provide for additional publication bodies.
Awarding authorities shall retain key documents related to a procurement procedure for at least three years from the date the award becomes effective. The documents to be retained include
a) the call for tenders;
b) the tender documents;
c) the minutes of the bid opening;
d) the correspondence related to the procurement procedure;
e) the minutes concerning the correction of bids;
f) the decisions made in the context of the procurement procedure;
g) the selected bid;
h) the data allowing for the reconstruction of a procurement procedure conducted electronically;
i) the documentation relating to procurements by direct agreement of public contracts subject to international agreements.
During their retention period, the documents must be treated confidentially, unless this agreement provides for their disclosure. Legal duties of information are reserved.
Within twelve months following the end of each calendar year, the cantons shall prepare, for the State Secretariat for Economic Affairs (SECO), electronic statistics on markets subject to international agreements that were awarded during the previous year.
The statistics shall contain at least the following information
a) the number and total value of public contracts awarded by each adjudicator, broken down into construction contracts, supply contracts, and service contracts, with an indication of the CPC or CPV codes;
b) the number and total value of public contracts awarded by direct agreement;
c) estimates for the data required under items a and b, accompanied by an explanation of the method used to develop the estimates, in cases where it is not possible to provide the data;
The total value indicated must include value-added tax.
The overall SECO statistics are accessible to the public, subject to data protection and the preservation of business secrets.
**The Awarding Authority Notifies its Decisions to Tenderers Either by Publication or by Individual Notification**
The awarding authority notifies its decisions to tenderers either by publication or by individual notification. Tenderers cannot invoke the right to be heard before the notification of the decision.
Decisions subject to appeal must be briefly motivated and indicate the available legal remedies.
The brief motivation of an award includes
a) the type of awarding procedure used and the name of the successful tenderer;
b) the total price of the winning bid;
c) the decisive characteristics and advantages of the winning bid;
d) if applicable, the reasons for resorting to the negotiated procedure.
The awarding authority cannot provide any information whose disclosure
a) would violate existing law or harm the public interest;
b) would harm the legitimate commercial interests of tenderers; or
c) could undermine fair competition among tenderers.
1. Decisions of the adjudicator may be appealed to the cantonal administrative court as the sole cantonal instance, at least when the market value reaches the threshold value determinative for the invitation procedure.
2. Appeals concerning the markets of higher cantonal courts fall directly under the jurisdiction of the Federal Supreme Court.
3. Foreign bidders can only appeal against decisions relating to markets not subject to international agreements if the state in which they are headquartered grants reciprocity.
Only the following decisions are subject to appeal
a) the call for tenders;
b) the decision concerning the choice of participants in the selective procedure;
c) the decision to register a bidder on a list or to remove them from it;
d) the decision concerning requests for disqualification;
e) the award;
f) the revocation of the award;
g) the suspension of the procedure;
h) the exclusion from the procedure;
i) the imposition of a sanction.
The requirements contained in the tender documents, whose significance is identifiable, can only be contested as part of an appeal against the call for tenders.
The provisions of this agreement relating to the right to be heard in the decision-making procedure, to the suspensive effect, and to the restriction of grounds for appeal are not applicable in the case of an appeal against the imposition of a sanction.
The decisions mentioned in paragraph 1, letters c and i, may be appealed regardless of the contract value.
For the rest, decisions made based on this agreement are not subject to appeal.
The conclusion of subsequent contracts within the meaning of Article 25, paragraphs 4 and 5, cannot be subject to appeal.
The appeal does not have a suspensive effect.
Upon request, the Cantonal Administrative Court may grant suspensive effect to the appeal if it appears sufficiently well-founded and no overriding public interest opposes it. Generally, there is only an exchange of written submissions regarding suspensive effect.
A request for granting of suspensive effect that is abusive or contrary to good faith is not protected. Claims for damages by the awarding authority and the selected bidder fall under the jurisdiction of the civil courts.
Unless otherwise provided by this agreement, decision-making and appeal procedures are governed by the provisions of the cantonal legislation on administrative procedure.
**Appeals, duly substantiated, must be submitted in writing within 20 days from the notification of the decision.**
Judicial holidays do not apply.
An appeal may be lodged for
a) violation of the law, including excess or abuse of discretionary power;
b) incorrect or incomplete ascertainment of relevant facts.
The appropriateness of a decision cannot be examined within the scope of an appeal procedure.
Only those who can demonstrate that they can and want to provide the requested services or equivalent services may appeal against direct awards. Only the improper application of the direct award procedure and the grievance that the award is tainted by corruption may be invoked.
During the decision-making procedure, bidders do not have the right to inspect the documents.
In the appeal procedure, the appellant may, upon request, inspect the documents related to the evaluation of their bid and other documents in the procedure that are decisive for the decision, unless there is an overriding public or private interest that opposes it.
The appellate authority may either render a decision itself or refer the case back to the previous authority or the adjudicator. In the event of a referral, it issues binding instructions.
When the appeal is well-founded and the contract has already been concluded with the selected bidder, the appellate authority acknowledges the unlawfulness of the decision.
At the same time as it acknowledges the breach of law, the appellate authority rules on any possible claim for damages.
Damages are limited to expenses that the bidder has incurred in relation to the preparation and submission of their offer.
When the appellate authority is called upon to rule on a request for revision, Article 60, paragraph 2, applies by analogy.
**The Monitoring of Switzerland's Compliance with International Public Procurement Commitments**
The oversight of Switzerland's adherence to international commitments concerning public procurement falls under the responsibility of the Confederation-Cantons Public Procurement Commission (CCPCC). This commission is comprised equally of representatives from the Confederation and representatives from the cantons. The secretariat is provided by SECO (State Secretariat for Economic Affairs).
The CCPCC specifically assumes the following tasks
a) to define Switzerland's position for the Federal Council within international bodies and to advise the Swiss delegations participating in negotiations;
b) to promote the exchange of information and experiences between the Confederation and the cantons and to develop recommendations for the transposition of Switzerland's international commitments into Swiss law;
c) to maintain contacts with foreign supervisory authorities;
d) to give advice and, in specific cases, to serve as a mediator in disputes related to the matters referred to in points a to c.
When there are indications that Switzerland's international commitments in the field of public procurement are being violated, the CCPCC may intervene with the authorities of the Confederation or the cantons, prompting them to clarify the situation and, in the case of confirmed irregularities, to take necessary measures.
The CCPCC may conduct expert assessments or have them carried out by experts.
It establishes its internal regulations, which must be approved by the Federal Council and by AiMp.
**Members of the Swiss Conference of Cantonal Directors of Public Works, Spatial Planning and Environmental Protection representing the cantons party to this agreement, constitute the Intercantonal Authority for Public Procurement (IAPP).**
The IAPP is responsible for the following tasks in particular
a) enacting the present agreement;
b) making amendments to the present agreement, subject to the approval of the cantons party to it;
c) adjusting threshold values;
d) proposing an exemption to the Federal Council regarding this agreement and acknowledging requests to that effect from the awarding authorities as per Article 7, paragraph 1 (exemption clause);
e) monitoring the implementation of this agreement by the cantons and appointing a control body;
f) maintaining the list of sanctioned bidders and subcontractors in accordance with Article 45, paragraph 3;
g) adopting regulations setting out the organizational and procedural rules for the implementation of this agreement;
h) acting as a contact body within the framework of international agreements;
i) appointing cantonal delegates to national and international commissions and approving their operational rules.
The IAPP makes its decisions by a three-quarters majority of the representatives present, provided that half of the cantons are represented. Each canton party to the agreement has one vote, which is expressed by a member of its government.
The IAPP collaborates with the Conferences of Heads of Relevant Cantonal Departments, with the Cantonal Specialized Conferences and with the Confederation.
The cantons ensure compliance with the present agreement.
The AiMp handles denunciations from cantons regarding compliance with the present agreement by other cantons.
Denunciations from individuals concerning compliance by the cantons with the present agreement are handled by the AiMp. Such denunciations do not confer party status and do not entitle the individual to a decision.
The AiMp issues regulations on this matter.
Each canton may accede to the present agreement by a simple declaration addressed to the AiMp.
The present agreement may be terminated at the end of a calendar year with a six-month notice addressed to the AiMp.
Any accession or termination, as well as any amendment or cancellation of the present agreement, shall be communicated to the Federal Chancellery by the AiMp.
In compliance with Switzerland's international commitments, the cantons may enact implementing provisions, particularly for Articles 10, 12, and 26.
**The Award Procedures Initiated Before the Entry into Force of This Agreement**
The award procedures that were initiated before the entry into force of this agreement are governed by the former law until their conclusion.
In the event of denunciation by a canton, the present agreement applies to public procurements that have been subject to a call for tenders before the end of the calendar year for which the denunciation is effective.
**1. Entry into Force**
This agreement enters into force as soon as two cantons have acceded to it. Its entry into force is communicated to the Federal Chancellery by AiMp.