Art. 58 BWRG · b) Decision

1. During the project approval process, the government decides on all additional outstanding permits required for the implementation of the project, particularly including the construction and exceptional permits according to planning law.

2. If all additional permits could already be granted with the concession approval decision, the project approval procedure is omitted.

← Art. 57 BWRG - 4. Project Approval Procedure Water Rights Act of the Canton of Grisons (BWRG) - Scope of Application Art. 59 BWRG - c) Public Display, Legal Remedies →