Art. 56 Water Rights Act of the Canton of Grisons (BWRG) - e) Public Display of the Authorization Decision, Legal Remedies
**Use of Hydropower - Procedure**
Art. 56 BWRG - e) Public Display of the Authorization Decision, Legal Remedies · e) Public Display of the Authorization Decision, Legal Remedies
1. The concession approval decision, the environmental impact report, and the assessment by the cantonal environmental protection agency will be made publicly available for a period of 30 days at the responsible department. Legal confidentiality obligations and the right to access the files by those entitled to appeal are reserved.
2. The publication must be announced in the Cantonal Official Gazette, with a reference to any additional permits that may have been granted.
3. The concession approval decision can be appealed to the Superior Court within 30 days. The right to appeal is also available to the municipalities.
Court Decisions Applying This Provision (3)
U 2006 93 · gr (Art. 56 Abs. 3 BWRG)
Power Company Hydropower Concession Renewal and Environmental Flow Standards Appeal
This article defined the right of appeal against the concession decision.
PVG 2004 29 · gr (Art. 56 Abs. 3 BWRG)
Appealability of Government-Approved Reversion Inventory under Water Management Law
The decision implies that the government's approval of the concession, which includes the inventory, is appealable to the Administrative Court.
U 2003 106 · gr (Art. 56 Abs. 3 BWRG)
Scope of Mandatory Transfer Inventory Following Water Power Concession Expiry
Mentioned as the legal basis for appealing the government's decision regarding the inventory to the Administrative Court (analogous to a concession approval decision).