Art. 26 Roads Act of the Canton of Graubünden (StrG) - Simplified Procedure
Art. 26 StrG - Simplified Procedure · Simplified Procedure
1. For locally limited projects or project modifications that affect a few, clearly identifiable property owners, do not affect any legitimate interests of third parties, and do not have a significant impact on land and the environment, the simplified procedure may be carried out. In cases of doubt, the regular procedure will be conducted.
2. In the simplified procedure, the public display is omitted. The Civil Engineering Office informs the municipality, affected property owners, and affected third parties about the project or the project modification. If they do not provide written consent, a 30-day objection period is granted to them.
3. The project documents are open for inspection by the affected parties during the objection period. The provisions regarding the objection procedure and the effect of the project approval apply accordingly.
4. If a publicly announced project is modified before the approval decision in the simplified procedure, it will be submitted to the government along with the corresponding changes for approval.
5. If the consents according to paragraph 2 are present in locally limited projects, government approval of the project is not required.