Legislator Case Law & Legislation
807.100 STRGLStra CH-GR

Art. 19 Roads Act of the Canton of Graubünden (StrG) - Condition Project 1. Components

**Planning and Construction**
Open official source Full Act (67 Articles) Machine-readable Markdown (.md)

Art. 19 StrG · Condition Project 1. Components

1. The necessary components of the planning projects for cantonal roads are determined by the government.

← Art. 18 StrG - 2. Exemptions Roads Act of the Canton of Graubünden (StrG) - Scope of Application Art. 20 StrG - 2. Public Display →

Need to analyze how this provision applies to your matter?

Cross-reference this statute against case law, commentaries, and related legislative provisions inside Legislator AI.

Open in Legislator →

Court Decisions Applying This Provision (1)

R 2019 19 · gr (Art. 19 ff. StrG)
Property Owners v. Canton: Road Construction Expropriation Upheld
Cited concerning the public display of cantonal road projects, relevant because the municipality argued that this procedure was not required for the local access road.