Art. 60 Spatial Planning Ordinance for the Canton of Graubünden (KRVO) - Control of Building Execution, Building Acceptance
Art. 60 KRVO - Control of Building Execution, Building Acceptance · Control of Building Execution, Building Acceptance
1. The municipal building authority reviews the execution of construction projects for their compliance with the building permit, the BAB permit, and any additional permits, insofar as the controls do not fall under the jurisdiction of the authorities responsible for the additional permits. It inspects at least the grid layout and the height reference points. Connections to public supply and disposal facilities are checked before covering.
2. The project owner immediately reports the completion of the construction to the municipal building authority. This authority conducts the building acceptance inspection. For construction projects outside the building zones, the municipal building authority reports to the specialized office whether the completed construction project conforms to the BAB permit. In the event of discrepancies, it forwards the execution plans to the specialized office.
3. The municipal building authority can appoint private parties to conduct construction inspections.
4. If a construction project is commenced without a building permit or deviates from approved plans or conditions in the building permit, the municipal building authority, in urgent cases, one of its members, or the head of the building department or the municipal clerk, orders the cessation of construction work. At the same time, the deciding authority or official requests the project owner to submit a subsequent building application.
5. Orders for the cessation of construction are immediately enforceable.