Formal Building Law - Building Permit Procedure - Standard Building Permit Procedure
Open official source Full Act (85 Articles) Machine-readable Markdown (.md)

Art. 49 KRVO · 3. Decision, Announcement

1. Upon receipt of all documents, the competent authority decides on the BAB application and any objections, and grants the BAB permit, provided that the legal requirements are met. Otherwise, it rejects the BAB application.

2. The competent authority decides on BAB applications within one month of receipt of the complete construction application documents. For construction projects that require internal administrative consultation or an additional permit, the processing period is a maximum of three months. For construction projects with objections, an Environmental Impact Assessment (EIA), or a particularly high need for coordination, the processing period is a maximum of five months.

3. BAB permits and any objection decisions are communicated to the applicants and objectors by the municipal building authority as soon as possible after receipt, but no later than within two weeks, together with the building permit.

4. The costs of the BAB procedure are invoiced in the BAB permit.

← Art. 48 KRVO - 2. Hearing, Settlement, Arbitration Tribunal Spatial Planning Ordinance for the Canton of Graubünden (KRVO) - Competent Department, Specialized Office Art. 49a KRVO - 4. Waiver of Statement of Reasons for Decision →

Need to analyze how this provision applies to your matter?

Cross-reference this statute against case law, commentaries, and related legislative provisions inside Legislator AI.

Open in Legislator →

Court Decisions Applying This Provision (1)

R 2013 175 · gr (Art. 49 cpv. 1 OPTC)
Municipality Excavation Material Removal Order Upheld
Cited in conjunction with other provisions to support the argument that municipal authorization for construction outside the building zone is subordinate to cantonal approval.