Art. 87 Spatial Planning Act for the Canton of Graubünden (KRG) - BAB Authorization, BAB Authority
Art. 87 KRG - BAB Authorization, BAB Authority · BAB Authorization, BAB Authority
1. Buildings and facilities outside building zones (BAB) require, in addition to a building permit, a cantonal permit (BAB permit).
2. Responsibility for decisions regarding construction projects outside building zones lies with the department (BAB authority). The government may delegate, by regulation, the responsibility wholly or partially to another cantonal authority.
3. The municipal building authority forwards applications for construction projects outside building zones (BAB application) for which it deems the prerequisites for a building permit and a BAB permit as fulfilled, with a substantiated request for the issuance of the BAB permit to the relevant office. Otherwise, it rejects the application on its own authority.
4. If the BAB authority grants the BAB permit, it is issued by the municipal building authority together with the building permit. In this case, the building permit may be appealed directly to the superior court, irrespective of any local legal remedies.
5. If the BAB authority denies the BAB permit, it directly issues the denying BAB decision to the applicants, whereby the building application is considered rejected. For the procedural costs of the municipality, the municipal building authority issues a separate cost decision.
6. Buildings and facilities that are exempt from the building permit requirement by regulation of the government do not require a BAB permit, even if the municipalities have subjected them to the simplified building permit procedure.