Art. 37 KRG - 5. Groundwater and Spring Protection Zones · 5. Groundwater and Spring Protection Zones
1. Groundwater and Spring Protection Zones encompass areas that must be protected from adverse effects to ensure the supply of drinking water.
2. Areas within the Groundwater and Spring Protection Zone are considered highly sensitive areas under water protection legislation. The authority responsible for granting permits submits construction applications to the competent specialized authority.
3. Agricultural, forestry, horticultural, and other uses must be conducted in such a manner that adequate protection of the waters is guaranteed.
Court Decisions Applying This Provision (4)
R 2004 126 · gr (Art. 37 KRG)
Municipal Council Development Plan Approval Overturned for Inadequate Environmental Measure Stipulation
Cited in the reasoning regarding the relevant procedure for the UVP, though the final decision does not explicitly cite it to justify the outcome, only procedural grounds and costs.
R 2004 55 · gr (Art. 37 Abs. 3 KRG)
Property Owners v. Canton over Underground Road Reservation in Land-Use Plan
Contextually relevant provision cited in the reasoning concerning the requirement for government approval for municipal zoning and planning documents.
PVG 2003 22 · gr (art. 37 cpv. 1 LPTC)
Right to be Heard Before Suspension of Land-Use Approval Procedures
Cited to establish that the people are the supreme decision-making body regarding local planning revisions.
PVG 2003 22 · gr (art. 37 cpv. 3–5 LPTC)
Right to be Heard Before Suspension of Land-Use Approval Procedures
Cited to define the Government's limited authority to review planning provisions presented by the municipality.