Art. 98 RPBR - Notification · Notification

1. The approval is transmitted along with the dossier of the applicant, the author of the plans, and in the ordinary procedure, to the municipality.

2. In the simplified procedure, the municipal council transmits a copy of the approval to the district officer, the consulted authorities, and, for constructions outside the building zone, to the BRPA.

3. Authorities generally use electronic transmission for communications. The regulations regarding the delivery of decisions are reserved.

← Art. 97 RPBR - Project Amendment Regulation Implementing the Act on Spatial Planning and Construction (ReLATeC) - General Provisions Art. 99 RPBR - Commencement of Construction Before Approval (Art. 144 RPBG) →

Need to analyze how this provision applies to your matter?

Cross-reference this statute against case law, commentaries, and related legislative provisions inside Legislator AI.

Open in Legislator →

Court Decisions Applying This Provision (2)

602 2020 15 · fr (art. 98 al. 1 ReLATeC)
Building Permit Appeal for Canteen Extension Noise Pollution
Cited in the reasoning when discussing the communication of the file, although the dispositive confirms the rejection.
602 2020 62 · fr (art. 98 al. 1 ReLATeC)
Appeal Regarding Supplementary Building Permit Modifications Confirmed
This provision on the communication of the permit file is cited while analyzing the appellant's right to be heard.