Art. 90 Regulation Implementing the Act on Spatial Planning and Construction (ReLATeC) - Examination of the Building Application
Art. 90 RPBR - Examination of the Building Application · Examination of the Building Application
1. The municipality examines the application both formally and materially; if necessary, it requests the required additions.
2. If a formal defect is identified, the application is returned to the applicant for correction. The municipality will not entertain a second application that contains formal defects.
3. If a project is clearly in conflict with public construction law or could only be approved with a deviation that has not been requested, the municipality notifies the applicant or the person representing them in writing. The procedure continues if the applicant or the representative informs the municipal authority within thirty days of being notified of the defect that they wish to proceed with the application. Otherwise, the application is considered withdrawn.