710.11
RPBRRELATEC
CH-FR
Art. 89 Regulation Implementing the Act on Spatial Planning and Construction (ReLATeC) - Submission of the Building Application
Buildings - Building Permit - Building Permit Procedure (Art. 137, 140, 144, 147-149 RPBG)
Art. 89 RPBR - Submission of the Building Application · Submission of the Building Application
1. The applicant initiates the procedure by submitting a building application using the application for the building permit procedure to the municipality.
2. All components of the application must be electronically recorded and submitted using the application for the building permit procedure.
3. The application must also be submitted in paper form.
4. The application must include all information and documents required for examination in accordance with the directorate's guidelines. The directorate ensures that the formal requirements for the simplified procedure are limited to the information necessary for the processing of the application. These guidelines also determine the number of dossiers that must be submitted in paper form.