Art. 84 RPBR · Following the Ordinary Procedure

1. Subject to the standard procedure, the following require a building permit

a) the construction of new buildings, the demolition (subject to Article 150 paragraph 1 RPBG), reconstruction, enlargement, and addition of stories;

b) alterations that could affect the strength of a building’s supporting structure or its elements worthy of protection;

c) changes in the use of spaces and modifications to facilities that could affect the environment, including, in particular, new facilities as defined in Article 2 paragraph 4 letter a of the Air Pollution Control Ordinance (LRV), substantially modified installations as defined in Article 8 paragraphs 2 and 3 of the Noise Abatement Ordinance (LSV), modified facilities as defined in Article 9 of the Ordinance on Protection Against Non-Ionizing Radiation (NISV), facilities subject to environmental impact assessment as per Article 10a of the Environmental Protection Act of October 7, 1983 (USG), and facilities that are hazardous to water. Article 85 paragraph 1 letter d remains reserved;

d) ...

e) ...

f) civil engineering works, such as embankments, excavations, noise barriers, pipelines, sewer systems, water intakes, the expansion of watercourses, and access to a public road;

g) gravel extraction, landfills, and quarries, as well as all facilities associated with these installations;

gbis) extraction of materials from public waters for which a brief environmental report must be prepared (Art. 58 GewR);

h) sports and recreational facilities, such as sports fields, ice rinks, harbors, public swimming pools and beaches, shooting ranges and facilities, motocross tracks, go-kart tracks, model railways, artificial snow facilities, camping, and caravan sites;

i) all facilities and works that significantly alter the form of the land or the appearance of a landscape, place, or neighborhood;

j) renovation works associated with a change in the soil;

k) gas stations, silos, and containers of any kind. Articles 85 paragraph 1 letter j and 87 paragraph 1 letter e2 number 1 remain reserved;

l) transmission facilities subject to the NISV;

m) greenhouses and tunnels intended for agriculture, vegetable, and horticulture for year-round operation.

← Art. 83a RPBR - Exceptions for Energy Renovations Regulation Implementing the Act on Spatial Planning and Construction (ReLATeC) - General Provisions Art. 85 RPBR - Requirement for Approval - Under the Simplified Procedure →

Need to analyze how this provision applies to your matter?

Cross-reference this statute against case law, commentaries, and related legislative provisions inside Legislator AI.

Open in Legislator →

Court Decisions Applying This Provision (4)

602 2022 1 · fr (art. 84 al. 1 let. i ReLATeC)
Challenge to Building Permit Requirement for Agricultural Land Installations
This provision determines the ordinary procedure to be applied for the building permit application that the court orders the appellant to file.
602 2021 32 · fr (art. 84 al. 1 let. b ReLATeC)
Building Permit Requirement for Extensive Interior Structural Alterations
This provision establishes that repairs and transformations modifying the structure of the building are subject to an ordinary building permit, which justifies the rejection of the appeal against the decision ordering the permit application.
602 2016 122 · fr (art. 84 let. c ReLATeC)
Prefectural Decision on Building Permit Procedure Upheld
This provision was used to justify that the ordinary procedure should be applied for the installation, which was the core subject of the rejected appeal.
602 2016 101 · fr (Art. 84 let. b et c ReLATeC)
Cantonal Court Annuls Building Permit for Commercial Quail Farm in Residential Zone
Cited in the reasoning to determine that the ordinary procedure was applicable in this case.