710.11
RPBRRELATEC
CH-FR
Art. 100 Regulation Implementing the Act on Spatial Planning and Construction (ReLATeC) - Definition of Commencement of Construction (Art. 145 RPBG)
Buildings - Building Permit - Building Permit Procedure (Art. 137, 140, 144, 147-149 RPBG)
Art. 100 RPBR - Definition of Commencement of Construction (Art. 145 RPBG) · Definition of Commencement of Construction (Art. 145 RPBG)
1. The works are deemed to have commenced insofar as they have been concretely and earnestly undertaken and bear a significance demonstrating that the owner has incurred substantial costs for their initiation and continuation, such as notably significant earthworks, construction of foundations, demolition of a building for a new construction, creation of sewerage systems.
2. If the works are not progressing sufficiently rapidly, the permit holder may demonstrate in other ways that he or she has the genuine intention to proceed with the works without delay.
Court Decisions Applying This Provision (1)
602 2023 149 · fr (Art. 100 al. 1 ReLATeC)
Prefect's Annulment of Building Permits Overturned Due to Erroneous Assessment of Work Commencement
The court found that the conditions of this article regarding the commencement of works for permit N°ddd were met, leading to the annulment of the decision regarding this permit.