Art. 92 Spatial Planning and Construction Act (LATeC) - Suspension of Proceedings

Spatial Planning - Local Planning - Planning Zones and Preliminary Effects of the Plans
Open official source Full Act (208 Articles) Machine-readable Markdown (.md)

Art. 92 RPBG - Suspension of Proceedings · Suspension of Proceedings

1. The municipality or the directorate may, by interim decision, suspend a detailed development plan procedure if the plan threatens to impair planning measures that are in preparation. The decision of the municipality can be appealed to the directorate.

2. The building permit authority may, ex officio or at the request of the municipality, suspend a building permit procedure by interim decision if structures or facilities are to be erected in building zones or neighborhoods for which the municipality intends to amend the existing plan or create a detailed development plan.

3. The suspension of the procedure shall not last longer than 2 years. If no public display has taken place by the end of this period, the procedure shall be resumed. The suspension of the procedure does not give rise to any claim for compensation.

← Art. 91 RPBG - Temporary Building Restriction Spatial Planning and Construction Act (LATeC) - Purpose Art. 93 RPBG - Duty to Provide Access →

Need to analyze how this provision applies to your matter?

Cross-reference this statute against case law, commentaries, and related legislative provisions inside Legislator AI.

Open in Legislator →

Court Decisions Applying This Provision (2)

602 2011 80 · fr (art. 92 al. 2 LATeC)
Appeal Dismissed Against Building Permit Approval Under Local Zoning Limits
The court rejected the request to suspend the building permit procedure because the condition of the municipality intending to modify the existing plan was not met.
602 2011 80 · fr (art. 92 al. 3 LATeC)
Appeal Dismissed Against Building Permit Approval Under Local Zoning Limits
The court rejected the request for suspension because the maximum two-year period would not be respected, rendering the measure unsuitable and disproportionate.