Art. 145 Spatial Planning and Construction Act (LATeC) - Validity of the Authorization

**Constructions - Construction, Demolition, Location Permit - Building Permit**
Open official source Full Act (208 Articles) Machine-readable Markdown (.md)

Art. 145 RPBG - Validity of the Authorization · Validity of the Authorization

1. The work must commence within 2 years after the granting of the permit; if this period expires without being used, the permit becomes void.

2. The senior official may extend the building permit twice upon written request from the applicant and after evaluation by the municipality, if important reasons exist and the conditions of the building permit have not changed. If necessary, the opinion of the office can be obtained.

← Art. 144 RPBG - Early Commencement of Construction Spatial Planning and Construction Act (LATeC) - Purpose Art. 146 RPBG - Revocation →

Need to analyze how this provision applies to your matter?

Cross-reference this statute against case law, commentaries, and related legislative provisions inside Legislator AI.

Open in Legislator →

Court Decisions Applying This Provision (1)

602 2021 143 · fr (art. 145 al. 2 LATeC)
Prefecture v. Construction Company on Building Permit Expiration
The court's decision to annul the prior decision and remit the case to the Prefecture implies that the Prefecture must now examine the request for prolongation based on this article.