914.600 IVÖB CH-BS

Art. 13 Intercantonal Agreement on Public Procurement (IVöB) - Recusal

General Principles
Open official source Full Act (65 Articles) Machine-readable Markdown (.md)

Art. 13 IVöB - Recusal · Recusal

1. No individuals may participate on behalf of the contracting authority or an expert panel in the procurement process if they

a) have a personal interest in a contract;

b) are married to, in a registered partnership with, or in a de facto domestic partnership with a vendor or a member of its organs;

c) are related or connected by marriage in a direct line or up to the third degree laterally with a vendor or a member of its organs;

d) act as representatives of a vendor or have worked on the same matter for a vendor; or

e) display a lack of the independence required for conducting public procurements due to other circumstances.

2. A request for recusal must be submitted immediately upon becoming aware of the grounds for recusal.

3. The contracting authority or the expert panel shall decide on requests for recusal, excluding the person concerned.

4. The contracting authority may stipulate in the call for tenders that vendors who are in a relationship constituting grounds for recusal with a member of the jury for competitions and study contracts are excluded from the procedure.

← Art. 12 IVöB Intercantonal Agreement on Public Procurement (IVöB) - Subject Matter Art. 14 IVöB - Prior Involvement →

Need to analyze how this provision applies to your matter?

Cross-reference this statute against case law, commentaries, and related legislative provisions inside Legislator AI.

Open in Legislator →

Court Decisions Applying This Provision (2)

VD.2018.10 · bs (Art. 13 lit. i der Interkantonalen Vereinbarung über das öffentliche Beschaffungswesen vom 15. März 2001 (IVöB; SG 914.500))
Public Procurement Challenge Regarding Waste Vehicle Tender Termination
Cited when analyzing the requirements for the justified termination of the procedure, particularly the need for important reasons.
VD.2016.69 · bs (Art. 13 Abs. 1 lit. i IVöB)
Challenge to Planning Contract Award Based on Key Personnel Evaluation Error
Cited in the reasoning regarding the possibility of abandoning the procedure due to excessive budgeting, which forms part of the context for price evaluation, but is not explicitly in the dispositive.