§ 11 Implementing Provisions of IWB Industrielle Werke Basel for services in the field of electricity - Connection Agreement

Grid Connection - Connection Procedure
Open official source Full Act (61 Articles) Machine-readable Markdown (.md)

§ 11 Implementation Provisions of IWB Industrielle Werke Basel for Services in the Field of Electricity · Connection Agreement

1. The terms and costs of the network connection are determined in a connection agreement.

2. The conditions offered by IWB for the connection agreement are valid for 3 months. In justified individual cases, IWB may stipulate a different validity period. If the client allows the deadline to lapse, the connection offer expires, and a new connection application must be submitted for the network connection.

← § 10 Implementation Provisions of IWB Industrielle Werke Basel for Services in the Field of Electricity Implementing Provisions of IWB Industrielle Werke Basel for services in the field of electricity § 12 Implementation Provisions of IWB Industrielle Werke Basel for Services in the Field of Electricity - Costs →

Need to analyze how this provision applies to your matter?

Cross-reference this statute against case law, commentaries, and related legislative provisions inside Legislator AI.

Open in Legislator →