421
STGB
CH-BL
§ 16 Rhine Ports Act - Supply Lines
The Port Area - Permit System
§ 16 Rhine Port Act · Supply Lines
1. The laying of energy transmission lines (electricity, gas, district heating), telecommunication, data transmission lines, and similar on parcels owned by the Canton requires a permit from the competent Directorate.
2. The Canton is entitled to grant concessions for the use of its public area and to levy fees. The amount of the fees is based on the corresponding fees for cantonal roads.
3. Federal legal provisions remain reserved.