Art. 14 Water Usage Act (WUA) - Utilization of Hydropower
Use of Public Water - Responsibilities
Art. 14 Water Usage Act (WUA) - Utilization of Hydropower · Utilization of Hydropower
1. The concession for the use of hydropower or for pumped storage is granted for a maximum possible output from generator capacity as follows
a) **\*** up to one megawatt by the competent authority of the BVD,
b) **\*** over one to three megawatts by the BVD,
c) over three to ten megawatts by the Government Council,
d) over ten megawatts by the Grand Council.
2. The competent authority of the BVD carries out insignificant changes to a concession, provided no increase in the maximum possible output from the generator is involved that would result in a different competency according to paragraph 1.