1. In the municipality, the eligible voters are responsible for the decision regarding the water construction plan. The municipal regulations may provide for the competence of the Greater Municipal Council or City Council.
2. In the municipal association and in the river regulation corporation, competence is determined according to the regulations.
3. The approved water construction plan is submitted to the Department of Construction and Transportation. A copy is sent to the Office of the Government Preceptor.
4. The responsible authority of the Department of Construction and Transportation approves the water construction plan if it is lawful, suitable, and in the public interest. It may amend an unlawful or unsuitable plan after hearing the parties involved during the approval process.
5. If the water construction plan contradicts the water directive plan, it is nevertheless considered suitable if it better fulfills the objectives of this law.
6. The responsible authority of the Department of Construction and Transportation simultaneously addresses objections. It generally issues the approval decision together with the decision on special permits. As far as these also fall within the competence of the Department of Construction and Transportation or one of its offices, they are deemed granted with the plan approval.