1. Applications for government contributions must be submitted to the Office for the Environment and Energy.

2. They must be submitted before the commencement of construction or implementation of the measure. Applications submitted at a later date will not be considered.

← Art. 47 Cantonal Energy Ordinance (KEnV) General Provisions Art. 49 Cantonal Energy Ordinance (KEnV) - Contribution Assurance →

Need to analyze how this provision applies to your matter?

Cross-reference this statute against case law, commentaries, and related legislative provisions inside Legislator AI.

Open in Legislator →

Court Decisions Applying This Provision (1)

140 2016 28 · be (Art. 48 Abs. 2 KEnV)
Subsidy Rejection Upheld Due to Missed Pre-Commencement Filing Deadline
The appeal was dismissed because the requirement to submit the application before the start of construction or implementation was not met, as stipulated in this article.