Art. 43 Decree on the Building Permit Procedure (Building Permit Decree, BPD) - Project Modifications During Procedure and During Construction Execution
Art. 43 Decree on the Building Permit Procedure (Building Permit Decree, BPD) - Project Modifications During Procedure and During Construction Execution · Project Modifications During Procedure and During Construction Execution
1. A project modification within the meaning of this provision occurs when the basic features of the construction project remain unchanged.
2. The building permit authority may, after hearing the parties involved and the third parties affected by the project modification, continue the process without renewed publication or allow the modification of the approved project without a new building application procedure, provided that public or substantial neighboring interests are not additionally affected.
3. If the project modification occurs during the building appeal procedure, the municipality, the opposing party, and the third parties affected by the project modification must be heard. The appeal authority may refer the matter back to the lower instance for further processing.
4. In appeal proceedings before the Administrative Court, project modifications are excluded. However, the Administrative Court reserves the right to refer the matter back to the lower instance for examination of a project modification or to conclude the appeal proceedings by settlement.
5. If the project modification occurs only during the construction phase, jurisdiction is determined solely by the modification. The law applicable at the time of submission of the project modification shall be applied.