1. A project modification within the meaning of this provision occurs when the basic features of the construction project remain unchanged.

2. The building permit authority may, after hearing the parties involved and the third parties affected by the project modification, continue the process without renewed publication or allow the modification of the approved project without a new building application procedure, provided that public or substantial neighboring interests are not additionally affected.

3. If the project modification occurs during the building appeal procedure, the municipality, the opposing party, and the third parties affected by the project modification must be heard. The appeal authority may refer the matter back to the lower instance for further processing.

4. In appeal proceedings before the Administrative Court, project modifications are excluded. However, the Administrative Court reserves the right to refer the matter back to the lower instance for examination of a project modification or to conclude the appeal proceedings by settlement.

5. If the project modification occurs only during the construction phase, jurisdiction is determined solely by the modification. The law applicable at the time of submission of the project modification shall be applied.

← Art. 42 Decree on the Building Permit Procedure (Building Permit Decree, BewD) - General Building Application General Provisions Art. 44 Decree on the Construction Permit Procedure (Construction Permit Decree, CPD) - Subsequent Requests for Exceptions →

Need to analyze how this provision applies to your matter?

Cross-reference this statute against case law, commentaries, and related legislative provisions inside Legislator AI.

Open in Legislator →

Court Decisions Applying This Provision (95)

100 2023 346 · be (Art. 43 Abs. 3 BewD)
Builder v. Bern Cantonal Construction and Transport Directorate (Sewage Pipe Road Setback)
Cited as a procedural step the lower authority must take upon returning the case (granting a hearing).
100 2023 346 · be (Art. 43 Abs. 4 BewD)
Builder v. Bern Cantonal Construction and Transport Directorate (Sewage Pipe Road Setback)
Cited in the reasoning for the decision to return the matter for the plaintiff to submit a project modification.
100 2021 161 · be (Art. 43 Abs. 4 BewD)
Neighbor Objection to Semi-Detached House Attic Expansion Upheld on Fire Safety Grounds
Used to justify the remand of the case to the lower authority for the examination of a project change.
100 2022 359 · be (Art. 43 Abs. 1 BewD)
Construction Company v. Cantonal Building Authority (Flight Safety Modifications)
Cited in the reasoning regarding the conditions for remanding the case, but not explicitly cited in the operative part (Ziff. 1-4).
100 2022 359 · be (Art. 43 Abs. 4 BewD)
Construction Company v. Cantonal Building Authority (Flight Safety Modifications)
The court applied the rule allowing it to refer the matter back to the lower authority based on this provision (Order 2).
100 2022 359 · be (Art. 43 Abs. 4 BewD)
Construction Company v. Cantonal Building Authority (Flight Safety Modifications)
The court exercised its power to remand the case to the lower authority to examine the project modification, as allowed by this article.
110 2024 166 · be (Art. 43 Abs. 3 BewD)
Appeal Regarding Substantive Review of Modified Building Permit
Cited as the legal basis for the decision to overturn the appealed decision and remit the case concerning the project modification to the lower authority.
110 2024 84 · be (Art. 43 Abs. 1 BewD)
Building Permit Appeal for Photovoltaic System on Historic Building
Used to define what constitutes a project amendment, which was accepted as the basis for the revised decision.
110 2024 84 · be (Art. 43 Abs. 2 BewD)
Building Permit Appeal for Photovoltaic System on Historic Building
Cited regarding the possibility of submitting a project amendment during the appeal proceedings.
110 2024 88 · be (Art. 43 BewD)
Appeal Against Multi-Family Housing Permit Regarding Boundary Wall and Environmental Concerns
Cited in the reasoning explaining why the project change is accepted and replaces the original application without initiating a new permit procedure.
110 2024 107 · be (Art. 43 BewD)
Appeal of Building Permit Moot Due to Revised Plans and Subsequent Approval
The court ruled on the project amendment, which is governed by this article.
110 2023 153 · be (Art. 43 BewD)
Neighbors' Challenge to Municipal Building Permit for External Heat Pump Dismissed on Noise Grounds After Project Modification
Cited in the dispositive to confirm the project amendment granted by the BVD.
110 2023 182 · be (Art. 43 BewD)
Appeal Regarding Municipal Building Permit for Terraced Houses Upheld Despite Challenges to Height, Setback, and Parking Regulations
Governs the procedure for submitting and assessing project changes during the appeal process.
110 2023 177 · be (Art. 43 BewD)
Appeal Concerning Expanded Wooden Terrace and Procedural Violations
Used to define the procedure for handling the project modification submitted during the appeal proceedings.
110 2023 141 · be (Art. 43 Abs. 3 BewD)
Appeal Quashed Due to Substantial Project Modification Requiring Renewed Review
Cited as a basis for upholding the decision to remand the matter to the lower authority for re-evaluation of the project modification.