Art. 41 Decree on the Building Permit Procedure (Building Permit Decree, BPD) - 2. Extension of Validity Period

Validity and Expiration of the Building Permit
Open official source Full Act (60 Articles) Machine-readable Markdown (.md)

Art. 41 Decree on the Building Permit Procedure (Building Permit Decree, BPD) - 2. Extension of Validity Period · 2. Extension of Validity Period

2. The request for an extension of a building permit must be published if the extension could affect significant public interests. If no publication occurs, the request must be communicated in writing to the neighbors and the former objectors affected by the extension.

3. Objections can only be directed against the extension. The building permit authority addresses the objections in its decision on the extension. A settlement hearing does not take place.

4. The decision on the extension can be appealed like a building decision.

← Art. 40 Decree on the Building Permit Procedure (Building Permit Decree, BPD) - Time Limit General Provisions Art. 42 Decree on the Building Permit Procedure (Building Permit Decree, BewD) - General Building Application →

Need to analyze how this provision applies to your matter?

Cross-reference this statute against case law, commentaries, and related legislative provisions inside Legislator AI.

Open in Legislator →

Court Decisions Applying This Provision (1)

110 2022 61 · be (Art. 41 Abs. 2 BewD)
Appeal Against Refusal to Extend Building Permit Validity
The case was remanded because the procedure required publication or written notification of the extension request to neighbors/objectors was apparently not completed.