1. Commencement of Time Limits

Validity and Time Limitation of the Building Permit
Open official source Full Act (60 Articles) Machine-readable Markdown (.md)

Art. 40 Decree on the Building Permit Procedure (Building Permit Decree, BPD) - Time Limit

2. The commencement of the time limit for the building permit does not begin, or is suspended, if the building permit cannot be utilized due to legal reasons, and the building owner takes reasonable steps to remove the impediment.

3. After the removal of the impediment, the period shall continue for at least one more year.

← Art. 39 Decree on the Building Permit Procedure (Building Permit Decree, BPD) - Early Commencement of Construction General Provisions Art. 41 Decree on the Building Permit Procedure (Building Permit Decree, BPD) - 2. Extension of Validity Period →

Need to analyze how this provision applies to your matter?

Cross-reference this statute against case law, commentaries, and related legislative provisions inside Legislator AI.

Open in Legislator →

Court Decisions Applying This Provision (1)

120 2018 19 · be (Art. 40 Abs. 2 BewD)
Appeal Regarding Lapse of Building Permit for Unauthorized Construction
Cited in the reasoning regarding the condition under which the deadline for the building permit is suspended or does not begin (i.e., legal obstacles).