Art. 39 Decree on the Building Permit Procedure (Building Permit Decree, BPD) - Early Commencement of Construction

Validity and Duration of the Building Permit
Open official source Full Act (60 Articles) Machine-readable Markdown (.md)

Art. 39 Decree on the Building Permit Procedure (Building Permit Decree, BPD) - Early Commencement of Construction · Early Commencement of Construction

1. The building permit authority may allow construction to begin already after the expiration of the objection period, provided that the outcome of the proceedings cannot affect the work.

2. If the construction project must be assessed by multiple authorities, all must agree to the early commencement of construction.

3. If the construction project is based on building regulations that have not yet been approved, early commencement of construction can only be permitted if the competent body of the Directorate of Internal Affairs and Justice agrees.

4. Excavation of the construction pit, laying of pipelines, and similar work may be allowed by the municipal authority immediately upon receipt of the building application, provided there is no risk of impairing water resources and the applicants commit to restoring the natural state of the construction site if the building permit is denied. The permission may be made contingent upon the applicants providing adequate security for the fulfillment of this obligation.

← Art. 38 Decree on the Building Permit Procedure (Building Permit Decree, BewD) General Provisions Art. 40 Decree on the Building Permit Procedure (Building Permit Decree, BPD) - Time Limit →

Need to analyze how this provision applies to your matter?

Cross-reference this statute against case law, commentaries, and related legislative provisions inside Legislator AI.

Open in Legislator →