1. Within seven working days after the expiration of the objection period, the building permit authority shall provide a copy of the objections and legal precautions to the applicants and the affected authorities.
2. They shall have the opportunity to submit a written statement within ten days, or at the latest until the reconciliation hearing, if such a hearing is conducted.
3. In cases of clearly inadmissible or unfounded objections, the building permit authority may waive the need to obtain statements.