Art. 31 Decree on the Building Permit Procedure (Building Permit Decree, BewD) - Deadline and Form

1. Objection, Legal Preservation
Open official source Full Act (60 Articles) Machine-readable Markdown (.md)

Art. 31 Decree on the Building Permit Procedure (Building Permit Decree, BewD) · Deadline and Form

1. The objection period is 30 days and begins with the first publication or with the delivery of the written notification.

2. Objections must be submitted in writing, with reasons provided, in duplicate, to the building permit authority.

3. ...

← Art. 28 Decree on the Building Permit Procedure (Building Permit Decree, BPD) - Conditions General Provisions Art. 32 Decree on the Building Permit Procedure (Building Permit Decree, BPD) - Legal Protection →

Need to analyze how this provision applies to your matter?

Cross-reference this statute against case law, commentaries, and related legislative provisions inside Legislator AI.

Open in Legislator →

Court Decisions Applying This Provision (1)

110 2021 33 · be (Art. 31 Abs. 2 BewD)
Administrative Rejection of Building Permit Appeal Due to Unsubstantiated Initial Objection
Cited in the reasoning regarding the requirement for written objections to contain grounds.