Art. 18 Decree on the Building Permit Procedure (Building Permit Decree, BPD) - Examination by the Building Permit Authority
Art. 18 Decree on the Building Permit Procedure (Building Permit Decree, BPD) - Examination by the Building Permit Authority · Examination by the Building Permit Authority
**1. If, upon preliminary examination, the building permit authority identifies formal defects, it returns the application for improvement. It sets a reasonable deadline, advising that the application will be considered withdrawn if it is not resubmitted within that period.**
**2. If it is readily apparent that a construction project could not be approved under public law regulations, or only with exceptions that have not been requested, the building permit authority notifies the applicants of this deficiency. It offers them the opportunity to make improvements within three months, noting that the application will be considered withdrawn if it is not resubmitted within that period.**
**3. The return for improvement according to paragraphs 1 and 2 takes place within ten working days following receipt by the building permit authority.**
**4. The building permit authority will not proceed with a resubmitted application that is formally defective. If it has obvious material defects for which the authority itself is responsible for assessing, it will reject the application within 30 days.**