Art. 17 Decree on the Building Permit Procedure (Building Permit Decree, BPD) - Review by the Municipal Administration
Preliminary Examination
Art. 17 Decree on the Building Permit Procedure (Building Permit Decree, BPD) · Review by the Municipal Administration
1. Within seven working days after receipt of the building application and after the profiling has been completed, the municipal administration shall conduct a preliminary formal examination of the building and exception applications and forward them, indicating any uncorrected deficiencies, to the building permit authority. It may arrange for simple defects to be corrected beforehand.
2. If the preliminary examination reveals that the building decision falls within the jurisdiction of the small municipality, procedures set forth in Article 9 paragraphs 3 and 4 shall be followed.
3. In any case, the municipal administration shall ensure the immediate correction of erroneous or insufficient profiles.