Art. 10 Decree on the Building Permit Procedure (Building Permit Decree, BPD) - Building Application 1. Form
Art. 10 Decree on the Building Permit Procedure (Building Permit Decree, BPD) · Building Application 1. Form
1. The building application must be completed and submitted using the cantonal transmission system.
2. It must be signed by the building owner, the project authors, and additionally by the landowner if the construction is on someone else's land.
3. The site plan (Art. 12 and 13), the project plans (Art. 14), and any other necessary documents (Art. 15) must be submitted with the building application.
3a. For all construction projects, information on earthquake safety must be submitted with the required enclosures.
4. If the approval of the construction project requires the granting of an exception, an application for this must be included in the building submission. The request for an exception must be justified.
5. For construction projects subject to energy or environmental protection legislation, the required documents must be submitted.
6. The application documents with the plans must be submitted to the municipality in two paper copies, dated and signed. These are legally binding. The building permit authority may request additional copies.