Art. 62 Building Act (BauG) - Requirements, Jurisdiction, Duration
Art. 62 Building Act (BauG) · Requirements, Jurisdiction, Duration
1. As a planning zone within the meaning of the Federal Act on Spatial Planning, areas can be designated for which development plans (Art. 57 para. 2) must be issued or adapted.
2. If the prospective builders have submitted a building application or have communicated their intention to build in the form of a preliminary project, the planning zone must be established within three months. Otherwise, a planning zone in respect of the same project may only be declared by the governmental authority that has been notified of the project as a building application or preliminary project, for a period of five years, only if circumstances have changed significantly in the meantime.
3. The municipal council, the competent body of the regional conference, the competent department of the Building and Transport Directorate, and the competent department of the Directorate of Internal Affairs and Justice can issue planning zones for two years. The municipality can issue planning zones for land-use plans of local planning; the regional conference can issue regional planning zones for regional development ordinances; the canton can issue cantonal planning zones for land-use plans of cantonal planning such as road plans, cantonal development ordinances, substitute measures according to Article 65 paragraph 2 letter c, or water construction plans.
4. The duration of a planning zone can be extended by one year, for comprehensive revisions of local planning or complex other planning, to a maximum of five years if it is demonstrated that the new plans and regulations could not be established within the original timeframe.
5. Responsibility for granting an extension rests with
a) the competent authority of the Directorate of Internal Affairs and Justice for municipal and regional planning zones,
b) the directorate responsible for the authority that imposed the planning zone for cantonal planning zones.