Art. 2a Building Act (BauG) - Coordination
Art. 2a Building Act (BauG) · Coordination
1. The coordination of the building permit procedure with other procedures is governed by the Coordination Act.
2. Exempted are the building permit procedures conducted by the small municipality (Art. 33 Para. 2). For these, the following applies
a) The building permit shall only be issued once the additional approvals required for the construction project under other laws are obtained.
b) The building permit authority may deviate from letter a if a different sequence of approvals is more appropriate for specific reasons; in this case, Article 38 Paragraph 4 Letter a applies.
c) The municipality processes the building applications without delay. Provided it has the necessary documents, the building permit authority decides within 30 days.
d) If, in addition to the building permit, other permits are contested, the procedures are consolidated in the building appeal procedure and resolved with a comprehensive decision.