Art. 108 Construction Act (BauG) - Jurisdiction; Development Program
Art. 108 Construction Act (BauG) - Jurisdiction; Development Program · Jurisdiction; Development Program
1. The municipality plans and constructs the development infrastructure, unless there are special development carriers responsible, or if construction by property owners has been agreed upon.
2. The construction zone must be fully developed within 15 years from the date the approval becomes legally binding.
3. The municipal council decides on the development program. This program outlines how, when, and with what total costs the development, its expansion, or replacement will occur in each phase.
4. The municipality adapts the development program to changed circumstances; however, it may remove a planned development from the program only with the consent of the owners who have a right to development according to Article 108a.
5. If a special development carrier is delayed in constructing a development infrastructure, the municipality may, after an unsuccessful reminder, build the infrastructure itself at the cost of the development carrier. Complaints against decisions concerning the substitution of performance may be filed with the competent professional directorate. Decisions on such complaints can be challenged at the Administrative Court.