Art. 79h Act Concerning the Introduction of the Swiss Civil Code (EG ZGB) · 1.7 Retaining Walls and Slopes 1.7.1 Obligation to Construct; Execution

1. Whoever carries out embankments or excavations along the border is required to secure the neighboring property with slopes or retaining walls.

2. Slope gradients may not exceed 45° (100%). In steep terrains, naturally formed or sufficiently secured steeper slopes are permitted.

3. The retaining wall may be built at the border. If it serves the purpose of embankment, it may not exceed the natural ground level of the higher-lying property by more than 1.20 meters.

← Art. 79g Introductory Act to the Swiss Civil Code (EASCC) 1 President of the Municipal Council Art. 79i Federal Act on the Introduction of the Swiss Civil Code (EG ZGB) - 1.7.2 Property →

Need to analyze how this provision applies to your matter?

Cross-reference this statute against case law, commentaries, and related legislative provisions inside Legislator AI.

Open in Legislator →

Court Decisions Applying This Provision (1)

100 2022 303 · be (Art. 79h Abs. 3 EG ZGB)
Property Owner v. Municipality Regarding Unauthorized Retaining Wall Height and Terrain Elevation
Cited and used in the reasoning to assess the permissibility of the Römerstein wall height regarding public law compliance, influencing the finding that the works were likely not permit-eligible.