Art. 75 Act Introducing the Federal Acts on Environmental Protection and on the Protection of Waters - Provisional Groundwater Protection Zones

3. Section: Water Protection - III. Planning Protection
Open official source Full Act (88 Articles) Machine-readable Markdown (.md)

Art. 75 Environmental and Waters Protection Act; EWPA - Provisional Groundwater Protection Zones · Provisional Groundwater Protection Zones

1. If a project that requires approval under Art. 79 et seq. is located in an area where the groundwater protection zones and areas have only been provisionally designated, and it cannot be ruled out that the project contradicts groundwater protection, the municipal council shall establish a planning zone in accordance with the building law.

2. The responsible authorities, in whose interest the provisional protection zone has been designated, shall examine whether the area can be released from protection. If this is not possible, the procedure required for definitive protection under Art. 71 must be initiated without delay.

← Art. 74 Environmental and Water Protection Act; EWPA - Costs and Compensation Act Introducing the Federal Acts on Environmental Protection and on the Protection of Waters - Purpose and Scope Art. 76 Environmental and Water Protection Act; EWPA - Tank Register →

Need to analyze how this provision applies to your matter?

Cross-reference this statute against case law, commentaries, and related legislative provisions inside Legislator AI.

Open in Legislator →